History
  • No items yet
midpage
Edge Construction Co. v. United States
95 Fed. Cl. 407
Fed. Cl.
2010
Read the full case

Background

  • Edge sues the Government for breach of contract and wrongful termination related to a VA cemetery project worth $8,691,000.
  • Contract incorporated FAR disputes, default, and changes clauses; Government terminated for default on Sept. 9, 2005.
  • Edge sought eight equitable-adjustment claims (Counts I–VIII) for alleged changes and weather-related delays.
  • Edge challenged default termination and sought conversion to termination for convenience (Counts IX–X).
  • The court granted partial summary judgment for the Government on some counts and denied on others, with key disputes over scope, costs, and weather-related adjustments.
  • A 63-day weather-related extension was granted for the ETA period; the ETA was completed mid-2005, with completion date contested.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Edge provided a reasonable basis for equitable adjustments (Counts I, II, IV) Edge asserts actual cost data sufficient for equitable adjustments. Government contends Edge failed to substantiate increased costs with proper data. Genuine issues of material fact preclude summary judgment.
Whether the additional work (Counts III and V) fell within the contract scope Edge contends some items were outside the original scope. Court should interpret scope; government argues items are within scope. Counts III and V summary judgment for Government warranted.
Whether Edge is entitled to compensation for unusually severe weather (Counts VI–VIII) Edge claims extended delays and lost productivity due to severe weather. Weather delays are excusable but not compensable absent government-caused delays. Counts VII and VIII granted to Government; Count VI unresolved due to factual disputed weather extents.
Whether the termination for default was proper (Counts IX–X) Edge argues termination was improper and should be converted to termination for convenience. Termination justified if no reasonable likelihood of completion within time. Summary judgment denied due to factual disputes on completion date and remaining time.

Key Cases Cited

  • Wunderlich Contracting Co. v. United States, 351 F.2d 956 (U.S. Court of Claims, 1965) (actual-cost method; reasonable basis for damages)
  • Daly Construction, Inc. v. Garrett, 5 F.3d 520 (Fed. Cir. 1993) (need for reasonable method for computing damages)
  • H.B. Mac, Inc. v. United States, 153 F.3d 1338 (Fed. Cir. 1998) (contract interpretation; scope determinations)
  • Ace Constructors, Inc. v. United States, 499 F.3d 1357 (Fed. Cir. 2007) (contract interpretation and equitable adjustments)
  • Fraser Constr. Co. v. United States, 384 F.3d 1354 (Fed. Cir. 2004) (constructive acceleration and weather-related delays)
  • Broome Constr. Inc. v. United States, 492 F.2d 835 (Ct.Cl. 1974) (unusually severe weather; extensions of time)
  • McDonnell Douglas Corp. v. United States, 323 F.3d 1006 (Fed. Cir. 2003) (default termination; factual inquiries)
  • Danzig v. AEC Corp., 224 F.3d 1333 (Fed. Cir. 2000) (government-imposed delay; compensable delay)
  • Lisbon Contractors, Inc. v. United States, 828 F.2d 759 (Fed. Cir. 1987) (standard for reviewing default terminations)
  • Cape Ann Granite Co. v. United States, 100 Ct.Cl. 53 (Ct.Cl. 1943) (unusually severe weather determination)
Read the full case

Case Details

Case Name: Edge Construction Co. v. United States
Court Name: United States Court of Federal Claims
Date Published: Oct 29, 2010
Citation: 95 Fed. Cl. 407
Docket Number: No. 06-635C
Court Abbreviation: Fed. Cl.