History
  • No items yet
midpage
Ed Lally & Associates, Inc. v. DSBNC, LLC
145 Conn. App. 718
Conn. App. Ct.
2013
Read the full case

Background

  • From 2003 plaintiff Ed Lally & Associates provided engineering/surveying for a proposed subdivision involving properties at 30 and 33 Moosehom Road; original engagement was with D.H. Williams, Inc. and a developer (Shibley).
  • Over time Williams, Parks, Moosehom Road LLC and later DSBNC, LLC became involved; title transfers occurred between entities during the project period (2005–2009).
  • Plaintiff continued work and submitted a March 31, 2009 invoice and a reconciled July 2009 invoice showing $44,570.50 due; plaintiff filed mechanic’s liens for that amount on both properties and sued to foreclose the liens and for breach of contract and quantum meruit.
  • Trial court (court trial) awarded plaintiff foreclosure of both mechanic’s liens, breach of contract judgment against Moosehom, LLC and Parks, quantum meruit recovery against defendants, and prejudgment interest; law days were set and this appeal followed.
  • Defendants raised multiple defenses and counterclaims and repeatedly amended pleadings; the trial court struck several amended pleadings for procedural noncompliance and ultimately disallowed further late amendments on the grounds of prejudice and delay.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Subject-matter jurisdiction re: mechanic’s liens Lally: liens valid; court competent to adjudicate foreclosure Defendants: liens defective (wrong property, improper tacking, false statements, after-acquired property, filed late) and thus court lacked jurisdiction Court: jurisdiction not defeated; defects were merits/special-defense issues not jurisdictional and were not timely raised at trial, so claim not reviewed on appeal
Damages for breach of contract Lally: invoices, time slips, reconciliation, letter explanations and exhibit 53 support $44,570.50 with reasonable certainty Defendants: exhibit 53 insufficient and speculative; proof inadequate Court: ample evidence (invoices, time slips, reconciliation, testimony) supported damages; finding not clearly erroneous
Quantum meruit recovery alongside contract claim Plaintiff: alternative recovery; value equals contract award ($44,570.50) Defendants: cannot recover under both contract and quantum meruit for same subject matter Court: awarding both was error as to parties bound by express contract (Moosehom, Parks, D.H. Williams) but harmless (no double recovery); quantum meruit valid as to DSBNC, LLC based on implied contract/facts
Amendments / motions to strike pleadings Plaintiff: moved to strike deficient special defenses/counterclaims and objected to untimely/amended pleadings to prevent delay Defendants: pleadings were legally sufficient and plaintiff knew issues; procedural irregularities excused Court: defendants waived challenge to earlier strike by filing an amended pleading; trial court did not abuse discretion in denying late fourth amended pleadings due to delay/prejudice

Key Cases Cited

  • Louis Gherlone Excavating, Inc. v. McLean Construction Co., 88 Conn. App. 775 (discusses special defenses to foreclosure and raising validity issues)
  • Amodio v. Amodio, 247 Conn. 724 (distinguishes subject-matter jurisdiction from erroneous exercise of jurisdiction)
  • Artman v. Artman, 111 Conn. 124 (historical authority on jurisdiction vs. error in exercise of jurisdiction)
  • Duplissie v. Devino, 96 Conn. App. 673 (damage estimation standard: reasonable certainty)
  • David M. Somers & Associates, P.C. v. Busch, 283 Conn. 396 (quantum meruit vs. contract recovery; use of plenary review for equitable doctrines)
  • 300 State, LLC v. Hanafin, 140 Conn. App. 327 (quantum meruit/unjust enrichment principles; no recovery under quantum meruit where express contract governs)
  • Pamoff v. Mooney, 132 Conn. App. 512 (quantum meruit requires reasonable value when implied contract exists)
  • Noonan v. Noonan, 122 Conn. App. 184 (issue-preservation: appellate review requires issues raised and ruled on at trial)
  • Desrosiers v. Henne, 283 Conn. 361 (harmless error and harmfulness standard for excluded evidence)
  • Caltabiano v. L & L Real Estate Holdings II, LLC, 128 Conn. App. 84 (amending after motion to strike operates as waiver of appeal of the strike)
Read the full case

Case Details

Case Name: Ed Lally & Associates, Inc. v. DSBNC, LLC
Court Name: Connecticut Appellate Court
Date Published: Sep 17, 2013
Citation: 145 Conn. App. 718
Docket Number: AC 34497
Court Abbreviation: Conn. App. Ct.