History
  • No items yet
midpage
Echo Group v. Tradesmen Internat.
980 N.W.2d 869
Neb.
2022
Read the full case

Background

  • Lund-Ross was the general contractor on three projects; Signature (subcontractor) hired Echo Group to supply electrical materials. When Signature stopped operating, Echo recorded construction liens and sued property owners to foreclose.
  • Lund-Ross intervened and posted lien-release surety bonds in each case; Echo sought foreclosure of the liens and also pleaded unjust enrichment.
  • Each district court granted Echo summary judgment on the lien foreclosures. The courts varied on awarding prejudgment interest and attorney fees: one case awarded both, two denied prejudgment interest, and one denied fees.
  • Lund-Ross appealed from the summary judgments and from awards entered in excess of the surety bond or directly against Lund-Ross; Echo cross-appealed the denials of prejudgment interest and attorney fees in two matters.
  • The Nebraska Supreme Court consolidated the appeals and reviewed whether equitable balancing defeats summary judgment, whether judgments are limited by the surety bond, whether prejudgment interest is available, and whether attorney fees were authorized.

Issues

Issue Plaintiff's Argument (Echo) Defendant's Argument (Lund-Ross) Held
Whether equitable balancing prevents summary judgment on lien foreclosure Echo: It complied with the Construction Lien Act so summary judgment is appropriate. Lund-Ross: Because foreclosure is equitable, the court must balance equities before granting relief. Court: Equity "follows the law"; where statute defines rights and no material factual dispute exists, summary judgment is appropriate.
Whether recovery is limited to the amount of the surety bond Echo: Recovery may include amounts beyond bond where the Act authorizes them. Lund-Ross: Remedy is against the surety; judgment cannot exceed the bond penal sum. Court: Bond substitutes collateral and does not cap recoverable amounts the Act otherwise authorizes; excess may be awarded against principal.
Whether prejudgment interest is authorized on construction lien foreclosures Echo: Prejudgment interest allowed under §45-104 and §45-103.02(2); claims were liquidated. Lund-Ross: The lien or contracts are not proper "instruments in writing" or interest is not available. Court: Prejudgment interest is authorized under §45-104 (and §45-103.02(2) for liquidated claims); interest runs from recording of the lien; denials in two cases were reversed.
Whether attorney fees were recoverable under §52-157 or §44-359 Echo: Fees recoverable under §52-157(3) (remedies for wrongful conduct) and §44-359 (actions on insurance/surety policies). Lund-Ross: Statutes do not authorize fees here; Echo did not sue on the bond/insurance policy. Court: Fees not authorized under the circumstances: §52-157 awards fees only as part of damages for wrongful conduct (not automatic to prevailing lien claimant) and §44-359 requires an action on the policy/bond; fee awards reversed.

Key Cases Cited

  • Goes v. Vogler, 304 Neb. 848 (Neb. 2020) (describing mechanic/construction lien foreclosure as an equitable proceeding)
  • Lincoln Lumber Co. v. Lancaster, 260 Neb. 585 (Neb. 2000) (discussing remedies and equities related to construction liens)
  • Ag Valley Co-op v. Servinsky Engr., 311 Neb. 665 (Neb. 2022) (summary judgment standards and evidentiary burdens)
  • McGill Restoration v. Lion Place Condo. Assn., 309 Neb. 202 (Neb. 2021) (standard of review for prejudgment interest awards)
  • Walker v. Collins Construction Co., 121 Neb. 157 (Neb. 1931) (prejudgment interest allowed in lien contexts under §45-104)
  • O'Keefe Elevator v. Second Ave. Properties, 216 Neb. 170 (Neb. 1984) (prejudgment interest on mechanic's lien where money was withheld)
Read the full case

Case Details

Case Name: Echo Group v. Tradesmen Internat.
Court Name: Nebraska Supreme Court
Date Published: Oct 28, 2022
Citation: 980 N.W.2d 869
Docket Number: S-21-729, S-21-730, S-21-770
Court Abbreviation: Neb.