Eagle CDI, Inc. v. Michael J. Orr
E2016-01399-COA-R3-CV
| Tenn. Ct. App. | May 31, 2017Background
- The Orrs contracted with Eagle CDI to build a log cabin (Construction Contract, Feb. 1, 2013) and paid a $45,000 payment described on an invoice as a “NON-REFUNDABLE CUSTOMER DEPOSIT/RETAINER.”
- Disputes arose after invoiced charges went unpaid (Nov. 6, 2013 invoice $31,382.81; Feb. 27, 2014 invoice $91,187.01). Eagle continued work; the Orrs obtained certificate of occupancy and sought permanent financing.
- At closing on Feb. 28, 2014 the Orrs signed a Promissory Note for $122,569.82 (the exact sum of the two unpaid invoices). The Note: one lump-sum due in 30 days, 10% interest, 5% late fee; it made no reference to the Construction Contract or the $45,000 payment.
- The Orrs largely failed to pay the Note (one partial payment of $11,594.21); Eagle demanded payment and sued on the Promissory Note (Oct. 6, 2014). The Orrs initially answered pro se admitting signing and default but disputed the balance.
- The Orrs later (two weeks before trial, after obtaining counsel) moved to amend their answer to add affirmative defenses of duress and fraud; the trial court denied the motion for undue delay and later entered judgment for Eagle for principal, interest, fees, and attorneys’ fees. The Orrs appealed.
Issues
| Issue | Plaintiff's Argument (Eagle) | Defendant's Argument (Orrs) | Held |
|---|---|---|---|
| Whether the $45,000 initial payment must be credited against the Promissory Note balance | The Note is a separate, clear, unambiguous obligation for $122,569.82 (the two unpaid invoices); the $45,000 payment is not referenced and therefore not creditable | The $45,000 was a deposit/retainer under the Construction Contract and should be credited toward amounts later secured by the Note | The $45,000 was not credited; the Promissory Note was unambiguous and independent, so the Orrs breached and owe the Note amount plus permitted fees and interest |
| Whether the trial court abused discretion by denying the Orrs’ motion to amend their answer to assert duress/fraud | Denial was proper given undue delay, lateness (two weeks before trial), prejudice, and potential futility | The Orrs argued the defenses were meritorious and should be allowed despite timing | Denial affirmed: court did not abuse discretion; amendment was untimely and prejudicial |
Key Cases Cited
- Kafozi v. Windward Cove, LLC, 184 S.W.3d 693 (Tenn. Ct. App. 2005) (contract interpretation: intent determined from language when terms are definite)
- Planters Gin Co. v. Fed. Compress & Warehouse Co., Inc., 78 S.W.3d 885 (Tenn. 2002) (literal meaning controls when contract is unambiguous)
- Doe v. HCA Health Servs. of Tenn., Inc., 46 S.W.3d 191 (Tenn. 2001) (contracts interpreted from parties’ expressed intent in the text)
- Campora v. Ford, 124 S.W.3d 624 (Tenn. Ct. App. 2003) (parol evidence cannot vary clear, unambiguous contract terms)
- Pratcher v. Methodist Healthcare Memphis Hosps., 407 S.W.3d 727 (Tenn. 2013) (factors for granting leave to amend: undue delay, bad faith, repeated failures, futility)
