E-Z Roll Off, LLC v. County of Oneida
800 N.W.2d 421
Wis.2011Background
- E-Z Roll Off sued Oneida County over a Waste Management contract that reduced the tipping fee to $5.25/ton for Waste Management, while other haulers paid $54.00/ton.
- The contract also required Waste Management to remove loaded transfer trailers and pay $24.50/ton for disposal; E-Z alleged this violated Wis. Stat. § 133.03(1) and sought § 133.18 damages.
- Oneida County argued E-Z failed to meet Wis. Stat. § 893.80 notice-of-claim requirements, and the circuit court granted summary judgment for the County.
- The court of appeals reversed, holding that antitrust actions under § 133.18 are exempt from § 893.80(1) notice requirements.
- The Wisconsin Supreme Court granted review to decide whether § 133.18 actions are exempt and whether E-Z met notice requirements.
- The majority held that § 133.18 actions are not exempt and that E-Z did not file timely notice; the circuit court’s summary judgment was proper.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Are § 133.18 antitrust actions exempt from § 893.80(1) notice? | E-Z contends § 133.18 is a specific statutory scheme exempting its claim. | Oneida County argues no exemption; § 893.80(1) applies generally. | Not exempt; § 133.18 actions must comply with § 893.80(1). |
| Was E-Z's notice of claim filed within 120 days of the event? | Discovery of the contract in Feb. 2004 tolled accrual; notice within 120 days of discovery. | Event occurred at contract signing (June 25, 2003); notice by Sept. 28, 2005 was untimely. | Untimely; notice filed long after 120 days. |
| Did actual notice and lack of prejudice save the claim? | County had actual notice and prejudice was not shown. | Even with potential actual notice, prejudice was not proved; burden on E-Z to show lack of prejudice. | E-Z failed to prove lack of prejudice; exception not satisfied. |
| Does the continuing-violation doctrine apply to notice-of-claim timing here? | Each higher tipping fee could trigger a new accrual under continuing violations. | Wisconsin law does not apply continuing-violation accrual to § 893.80 timing. | Rejected; continuing-violation doctrine does not apply to § 893.80 timing. |
Key Cases Cited
- Gillen v. City of Neenah, 219 Wis.2d 806 (Wis. 1998) (supports exemption where a statute allows immediate injunctive relief; not controlling for this antitrust claim)
- Town of Burke v. City of Madison, 225 Wis.2d 615 (Wis. 1999) (three-factor test for exemptions to § 893.80(1))
- Auchinleck v. Town of LaGrange, 200 Wis.2d 585 (Wis. 1996) (modifies broad application of § 893.80(1) exemptions)
- Nesbitt Farms, LLC v. City of Madison, 265 Wis.2d 422 (Wis. 2003) (recognizes three-factor framework for exemptions)
- Oak Creek Citizen's Action Comm. v. City of Oak Creek, 304 Wis.2d 702 (Wis. 2007) (applies Town of Burke framework to exemptions)
- Olsen v. Twp. of Spooner, 133 Wis.2d 371 (Wis. Ct. App. 1986) (defines prejudice inquiry under § 893.80(1)(a))
- Ecker Bros. v. Calumet Cnty., 2009 WI App 112 (Wis. Ct. App. 2009) (recognizes three-factor test for exemptions to § 893.80)
