History
  • No items yet
midpage
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165
Fed. Cl.
2015
Read the full case

Background

  • E&E Enterprises Global (an SBA 8(a) contractor) was awarded an IDIQ firm‑fixed price contract to install broadband/VSAT at DeCA commissaries; the contract included task orders, a termination‑for‑convenience clause, and an SBA notice provision.
  • The agency issued 14 task orders and paid well above the $5,000 minimum; the contract was terminated for convenience about eight months into performance.
  • E&E submitted a certified CDA claim (Nov. 2012) containing two labeled alternatives: Alternative I (termination‑for‑convenience settlement costs ~ $1.53M) and Alternative II (wrongful/bad‑faith termination damages ~ $2.27M). The CO awarded only ~$97,900 on Alternative I and denied Alternative II; final decision dated May 16, 2013.
  • E&E sued in the Court of Federal Claims (May 15, 2014) asserting four breach theories (each seeking $3,296,543.18): (Count I) breach of implied covenant of good faith and fair dealing; (Count II) wrongful termination/breach; (Count III) implied‑in‑fact contract/quantum meruit; (Count IV) express breach (failure to give SBA advance notice).
  • The government moved to dismiss under RCFC 12(b)(1) and 12(b)(6). The court resolved jurisdictional issues (same‑claim rule under the CDA) and plausibility of the remaining counts.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Counts were "same claim" presented to contracting officer E&E: Counts I, II, IV arise from same operative facts as administrative claim; CO had adequate notice Gov: Counts I, III, IV were not the same claims presented; therefore no CDA jurisdiction Court: Has jurisdiction over Counts I, II, IV; Count III dismissed for lack of jurisdiction (not presented to CO).
Nature/identity of certified claim and appealability of Alternative I E&E: The administrative submission should be read as a unified claim; complaint seeks termination‑related relief Gov: Alternative I and II are separate claims; CO decision on Alternative I is final and E&E did not appeal it Court: Alternative I and II are divisible; no appeal of CO decision on Alternative I appears in complaint; thus no jurisdiction to relitigate that CO award here.
Sufficiency/plausibility of Counts I & II (breach of implied covenant; wrongful termination) under RCFC 12(b)(6) E&E: Complaint alleges bad‑faith conduct and damages; damages need not be more granular at pleading stage Gov: Damages are vague or speculative (percentage‑of‑contract formula); failure to plead constructive‑change elements; IDIQ discretion precludes implied‑covenant claim Court: Counts I and II survive 12(b)(6); damages pleading and alleged theories are plausible at this stage; constructive‑change and discretion arguments insufficient to dismiss now.
Sufficiency/plausibility of Count IV (SBA advance notice) E&E: Delay in notifying SBA is part of pattern of bad faith and supports relief Gov: Six‑hour delay caused no plausible $3.3M injury; FAR notice benefits SBA, not contractor Court: Count IV dismissed with prejudice for failure to state a plausible claim (no causal link or contractor entitlement).

Key Cases Cited

  • Veridyne Corp. v. United States, 758 F.3d 1371 (Fed. Cir. 2014) (describing SBA 8(a) subcontracting role)
  • Travel Centre v. Barram, 236 F.3d 1316 (Fed. Cir. 2001) (IDIQ contracts obligate purchase only of minimum quantity)
  • Mason v. United States, 615 F.2d 1343 (Ct. Cl. 1980) (discussing IDIQ obligations)
  • Scott Timber Co. v. United States, 333 F.3d 1358 (Fed. Cir. 2003) (CDA "same claim" rule allows some variance if claims arise from same operative facts and seek same relief)
  • Reliance Ins. Co. v. United States, 931 F.2d 863 (Fed. Cir. 1991) (administrative claim must clearly notify CO of breach/good‑faith theory; dissimilar post‑CO theories not allowed)
  • Case, Inc. v. United States, 88 F.3d 1004 (Fed. Cir. 1996) (divisible parts of a certified claim seeking different sums are separate claims)
  • Bell/Heery v. United States, 739 F.3d 1324 (Fed. Cir. 2014) (implied duty of good faith and fair dealing applies to government contracts)
  • Centex Corp. v. United States, 395 F.3d 1283 (Fed. Cir. 2005) (duty of good faith and fair dealing implied in every contract)
  • Precision Pine & Timber, Inc. v. United States, 596 F.3d 817 (Fed. Cir. 2010) (implied covenant prevents government reappropriation of contract benefits)
Read the full case

Case Details

Case Name: E & E Enterprises Global, Inc. v. United States
Court Name: United States Court of Federal Claims
Date Published: Feb 27, 2015
Citation: 120 Fed. Cl. 165
Docket Number: 14-423C
Court Abbreviation: Fed. Cl.