E.B. Endres, Inc. v. Shwemmlein, C. & R.
665 MDA 2017
| Pa. Super. Ct. | Jan 4, 2018Background
- Christoph and Rita Schwemmlein (German residents) contracted with E.B. Endres, Inc. for major renovations to a Pennsylvania home; Endres provided a written proposal dated August 16, 2007 listing a $167,000 scope of work, which defendants did not sign.
- Defendants designated Klaus Jaeger (local friend) as their on-site agent to approve details and change orders because the Schwemmleins lived in Europe.
- During construction (Aug 2007–Mar 2008) there were 81 change orders increasing costs; Endres documented each change and provided copies to Jaeger. Total extra work exceeded the original lump sum.
- At defendants’ request, Endres prepared one or two year-end invoices in Dec. 2007 for tax purposes showing $230,000; defendants paid a total of $230,000 by Jan. 3, 2008. Endres’ letters stated those invoices were not final bills.
- Endres issued a final bill in June 2008 for $85,245.61, later adjusted to $83,596.57 after credits. Defendants refused to pay the final balance. Endres sued (2010) for breach of contract and unjust enrichment; bench trial in Jan. 2016; judgment for Endres confirmed and amended to add costs and pre-judgment interest.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether an oral/written contract existed and its terms | Endres: the August 16, 2007 written proposal was accepted by conduct; work proceeded under that offer and change-order protocol | Schwemmlein: no binding acceptance of the written $167,000 lump-sum; parties agreed orally/by invoice to time-and-materials or a different lump sum | Court: Found a contract based on the August 16 written offer accepted by conduct; change orders were handled by the parties and billed time-and-materials |
| Whether a later (Dec. 2007) $230,000 lump-sum agreement replaced prior arrangement | Endres: December invoices were tax documents only; no agreement to cap final price at $230,000 | Schwemmlein: the $230,000 invoices (and subsequent payments) reflected an agreed total price for the project | Court: Rejected defendants’ claim of a new lump-sum agreement; invoices were prepared for tax purposes and not a binding new contract |
| Whether plaintiff was limited to actual costs per Note 6 of the written offer | Endres: change orders and course of dealing established time-and-materials billing (with standard markups) rather than simple reimbursement of ‘‘actual costs’’ under contingencies | Schwemmlein: Note 6 or contract terms limit recoverable amounts to actual costs for extra work | Court: Interpreted Note 6 as applying only to defined hidden contingencies; extra work was billed and recoverable on time-and-materials as performed in practice |
| Whether prejudgment interest was proper | Endres: pre-judgment interest appropriate because final bill amount was ascertainable | Schwemmlein: no basis for prejudgment interest | Court: Awarded prejudgment interest as amount due was readily ascertainable (adjusted final bill) and within court discretion |
Key Cases Cited
- Levitt v. Patrick, 976 A.2d 581 (Pa. Super. 2009) (standard of appellate review for non-jury trials: trial court findings given deference).
- Cresci Constr. Servs., Inc. v. Martin, 64 A.3d 254 (Pa. Super. 2013) (pre-judgment interest review is for abuse of discretion; framework for awarding interest in contract cases).
- Somerset Cmty. Hosp. v. Allan B. Mitchell & Assocs., Inc., 685 A.2d 141 (Pa. Super. 1996) (pre-judgment interest compensates injured party for being deprived use of money rightfully due).
- Frank B. Bozzo, Inc. v. Electric Weld Div. of Spang Indus., Inc., 498 A.2d 895 (Pa. Super. 1985) (discretionary nature of pre-judgment interest when damages are unliquidated).
- AccuWeather, Inc. v. Thomas Broad. Co., 625 A.2d 75 (Pa. Super. 1993) (offer may be accepted by conduct).
- Sheely v. Beard, 696 A.2d 214 (Pa. 1997) (new-trial/weight of the evidence standard; verdict will not be upset for conflicting testimony absent results shocking to justice).
- Reid v. Ruffin, 469 A.2d 1030 (Pa. 1983) (elements of agency formation).
