History
  • No items yet
midpage
Duce Construction Company Inc. v. Carlson Bros Inc
2:17-cv-02173
C.D. Ill.
Sep 23, 2019
Read the full case

Background

  • Duce Construction subcontracted with Carlson Bros. to perform earthwork and utilities at two Champaign, IL projects.
  • Parties agree Carlson owes Duce $261,852.41 for work under the original subcontract; Duce also seeks an additional $85,871.75 for extra work.
  • Duce says Carlson’s project manager orally directed Duce to perform extra work without following the contract’s written change-order procedure; Duce continued to avoid schedule delays.
  • Carlson deposited $261,852.41 with an escrow agent; escrow will not release funds until Duce signs a lien waiver, which Duce refuses because of the $85,871.75 dispute.
  • Both sides moved for partial summary judgment: Carlson sought judgment that no interest/fees are owed and that the written change-order clause bars recovery; Duce sought judgment for the undisputed amount plus interest/fees and for the extra-work claim.
  • The court denied both motions, leaving factual questions (e.g., oral modification, entitlement to interest/fees) for later resolution.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Entitlement to interest and attorney fees on $261,852.41 Duce: contract allows interest and fees for amounts over 30 days past due; escrow hasn't released funds so Duce hasn’t been paid. Carlson: it timely deposited the funds with escrow; because Duce didn’t provide required final waivers, no amount is "due" under the contract so interest/fees don’t apply. Denied summary judgment to both. Court: contract’s final-waiver precondition means no contract-based interest/fees have accrued; non-contractual remedies (statutory/equitable prejudgment interest or fees) remain possible but were not decided now.
Recovery for $85,871.75 in extra work (oral modification vs written change-order clause) Duce: Carlson orally modified/enforced waiver of written change-order requirement by telling Duce to continue to avoid delay. Carlson: the subcontract’s written change-order provision precludes recovery absent a signed, prior written change order. Denied summary judgment to both. Court: Illinois law permits enforceable oral modifications even when contract forbids them; existence and terms of any oral modification are factual issues for the trier of fact.

Key Cases Cited

  • Celotex Corp. v. Catrett, 477 U.S. 317 (summary judgment standard)
  • Gracia v. Volvo Europa Truck, 112 F.3d 291 (summary judgment evidence burden in Seventh Circuit)
  • Brazinski v. Amoco Petroleum Additives Co., 6 F.3d 1176 (movant can win by showing opponent lacks evidence on issue)
  • Tadros v. Kuzmak, 277 Ill. App. 3d 301 (Illinois law permits oral modification despite contract prohibition)
  • A.W. Wendell & Sons, Inc. v. Qazi, 254 Ill. App. 3d 97 (same)
  • Berg & Associates, Inc. v. Nelsen Steel & Wire Co., 221 Ill. App. 3d 526 (same)
  • E.A. Cox Co. v. Road Savers Int'l Corp., 648 N.E.2d 271 (questions about modification/waiver are factual)
  • Maher & Assocs., Inc. v. Quality Cabinets, 640 N.E.2d 1000 (existence of modification by conduct is question of fact)
  • Household Fin. Servs., Inc. v. Coastal Mortg. Servs., Inc., 152 F. Supp. 2d 1015 (factual nature of oral-modification inquiry)
  • Platinum Tech., Inc. v. Federal Ins. Co., 282 F.3d 927 (availability of prejudgment interest under non-contractual theories)
Read the full case

Case Details

Case Name: Duce Construction Company Inc. v. Carlson Bros Inc
Court Name: District Court, C.D. Illinois
Date Published: Sep 23, 2019
Docket Number: 2:17-cv-02173
Court Abbreviation: C.D. Ill.