History
  • No items yet
midpage
Driver Pipeline Co. v. Cadeville Gas Storage, LLC
150 So. 3d 492
La. Ct. App.
2014
Read the full case

Background

  • Driver and Cadeville contract for Driver to construct pipelines for a storage facility; Cadeville to furnish materials and permits; completion deadlines February 2013; Driver delayed due to Cadeville’s material, permit, and related issues; Driver submitted change orders totaling over $3 million; Cadeville refused and later dispute led to suit May 31, 2013; Cadeville filed reconventional demand; partial summary judgment dismissed Change Orders 17–27; on appeal, Louisiana intermediate court reversed and remanded; underlying issue is whether oral/silence modifications to a written contract could override the written-change-order requirement; discovery disputes complicated proceedings.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the trial court correctly granted partial summary judgment on change orders 17–27 Driver contends genuine issues of material fact exist about necessity and approval of change orders. Cadeville argues contract required written change orders and that Driver ignored prior approvals. No; the court held there were genuine issues of material fact and the trial court erred in granting summary judgment.
Whether the contract’s modification clause barred oral or implied modifications Driver asserts the contract may be modified orally or by conduct despite an integration clause. Cadeville contends the integration clause precludes any modification not in writing. The court held that contract modification can occur orally or by silence/inaction despite an integration clause, and that summary judgment was improper.
Whether there was an oral modification or implied modification of the contract Evidence suggested parties paid for unapproved work and emails referenced modified responsibility. Cadeville relies on written terms and integration clause to deny modification. There are genuine issues of material fact as to whether an oral or implied modification occurred.
Whether modification law from other jurisdictions/contexts applies to construction contracts Established Louisiana jurisprudence allows oral modifications to written contracts; this should apply here. Some cited authorities rely on contexts (e.g., LMVSFA) or stand for limited propositions. Louisiana law permits oral or implied modifications to written construction contracts; trial court erred in rejecting them.

Key Cases Cited

  • Rhodes Steel Bldgs., Inc. v. Walker Const. Co., 813 So.2d 1171 (La.App.2d Cir.2002) (oral modification may occur despite writing requirement)
  • Salley v. Louviere, 162 So. 811 (La. 1935) (parol evidence not allowed to vary written contract but may show subsequent modification)
  • Wisinger v. Casten, 550 So.2d 685 (La.App.2d Cir.1989) (written contract can be modified by oral agreement and conduct)
  • Pelican Elec. Contractors v. Neumeyer, 419 So.2d 1 (La.App.4th Cir.1982) (modification by conduct or oral agreement possible when contract is silent on method)
  • Amitech U.S.A., Ltd. v. Nottingham Const. Co., 57 So.3d 1043 (La.App.1st Cir.2010) (modification by oral agreement or conduct permissible in construction contracts)
Read the full case

Case Details

Case Name: Driver Pipeline Co. v. Cadeville Gas Storage, LLC
Court Name: Louisiana Court of Appeal
Date Published: Oct 1, 2014
Citation: 150 So. 3d 492
Docket Number: No. 49,375-CA
Court Abbreviation: La. Ct. App.