History
  • No items yet
midpage
DISTRICT OF COLUMBIA v. DISTRICT OF COLUMBIA CONTRACT APPEALS BOARD, and PRINCE CONSTRUCTION CO., INC., and W.M. SCHLOSSER CONSTRUCTION CO., INC
145 A.3d 523
| D.C. | 2016
Read the full case

Background

  • The District contracted with Prince Construction Co. and W.M. Schlosser (joint venture) in 2006 to alter and expand the Fort Totten Solid Waste Transfer Facility; contract price was $13,266,000 and completion was set for July 17, 2007.
  • During performance the District directed unanticipated work captured in five change orders that increased the contract price by about $1,028,178 but granted only one day of time extension; project finished April 4, 2008 (261 days late).
  • Prince/Schlosser submitted claims for indirect delay costs (extended labor, overhead, lost profits, bond costs) and two direct-cost claims (wiring five truck scales and sulfate‑resistant concrete). Total CAB award: $585,498.98 plus interest.
  • The District argued the delay claims were procedurally barred because Prince/Schlosser did not (1) give written notice within 30 days after change orders and (2) submit certified cost‑or‑pricing data; it also disputed liability on the merits for specific items.
  • The CAB rejected the procedural defenses, awarded damages for seven claims, and Prince/Schlosser appealed to this court; the court reviews contract interpretation de novo but gives weight to the CAB.

Issues

Issue Prince/Schlosser's Argument District's Argument Held
30‑day written notice after change order Notice requirement should not bar claims because District had actual notice of delay circumstances from monthly schedule updates and other communications Strict enforcement of 30‑day clause bars late claims; alternatively, late notice prejudiced the District 30‑day requirement is liberally construed; claims not barred because District knew facts and was not prejudiced
Certified cost or pricing data (H.33.E) Post‑performance claims relied on actual incurred costs (verifiable records), not pre‑negotiation cost/pricing data; H.33.C.2 governs post‑performance payments Contractor failed to supply certified cost/pricing data required before negotiating price adjustments Claims not barred: when actual costs are incurred, contractor may submit records of actual costs rather than pre‑negotiation cost/pricing data
Storm drainage pipe relocation delay Relocation was an unforeseen site condition that caused delay and costs; CAB awarded indirect costs Change Order No. 3 expressly referenced the pipe work and included broad release language discharging the District from claims connected to that change order Reversed: Change Order No. 3 released the District from delay claims connected to the storm pipe work
Fire‑pump installation delay (fire‑suppression system) District’s drawings omitted pump; implied warranty of accuracy of design specs applies and District must pay delay costs Fire suppression was a performance specification (not a method/spec detail) so implied‑warranty rule does not apply; contractor assumed risk of method Reversed: the fire‑suppression requirement was a performance spec; no implied‑warranty recovery for delay costs from pump installation
Truck scales wiring (constructive change) District’s precontract reply suggested others would provide wiring; CAB awarded compensation for unexpected wiring Addendum answer referenced "two new scales," creating a nonresponsive or ambiguous answer; contractor had duty to inquire about the patent ambiguity Partially reversed: Addendum created a patent ambiguity; contractor failed to inquire and cannot recover for three scales, but District is liable for wiring of two scales that it ultimately required

Key Cases Cited

  • Tillery v. District of Columbia Contract Appeals Bd., 912 A.2d 1169 (D.C. 2006) (standard of review and deference to CAB interpretations)
  • Organization for Environmental Growth, Inc. v. District of Columbia (OFERGO I), 700 A.2d 185 (D.C. 1997) (discussion of CAB expertise and prior treatment of notice provisions)
  • White v. Edsall Construction Co., 296 F.3d 1081 (Fed. Cir. 2002) (distinguishing implied warranty for design specifications from performance specifications)
  • P.J. Dick Inc. v. Principi, 324 F.3d 1364 (Fed. Cir. 2003) (concurrent delay principles in federal contract law)
  • United States v. Cunningham, 125 F.2d 28 (D.C. Cir. 1941) (purpose of delay‑notice clauses: notify government of causes so it can act; prejudice requirement)
Read the full case

Case Details

Case Name: DISTRICT OF COLUMBIA v. DISTRICT OF COLUMBIA CONTRACT APPEALS BOARD, and PRINCE CONSTRUCTION CO., INC., and W.M. SCHLOSSER CONSTRUCTION CO., INC
Court Name: District of Columbia Court of Appeals
Date Published: Aug 18, 2016
Citation: 145 A.3d 523
Docket Number: 14-AA-396
Court Abbreviation: D.C.