History
  • No items yet
midpage
Developers Surety & Indemnity Co v. Cercontec L L C
5:18-cv-01379
W.D. La.
Mar 13, 2020
Read the full case

Background

  • Developers Surety & Indemnity Co. (Developers) and Cercontec, L.L.C. (Cercontec) executed an indemnity agreement on June 17, 2015; Kerry Williams signed individually as indemnitor but was later dismissed from this action.
  • Developers issued payment/performance bonds for two City of Shreveport projects (Bill Cockrell Pool House and Airport Park Pool House) for which Cercontec was the contractor.
  • Cercontec notified Developers in Aug./Sept. 2016 that it could not complete the contracts and was in default; claims were made against the bonds.
  • Developers paid subcontractors/suppliers ($52,206.23 and $94,502.58) and paid Claims Consulting Services $69,561.35 for investigation/consulting; it also incurred $6,296.40 in attorneys’ fees—total claimed $212,566.56 (net of a $10,000 recovery).
  • Cercontec’s counsel withdrew, Cercontec failed to obtain new counsel, the court struck its answer, the clerk entered default, and Developers moved for default judgment for breach of the indemnity agreement.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Appropriateness of default judgment Developers: Cercontec failed to respond/enroll counsel; default entered; judgment appropriate. Cercontec: no responsive argument (failed to defend). Court granted default judgment; circumstances (no material fact dispute, prejudice, no excusable neglect) weigh in favor.
Enforceability of the indemnity agreement under Louisiana law Developers: Agreement is clear, unambiguous, and requires Cercontec to indemnify for all losses arising from issuing bonds, including counsel and consultant costs. Cercontec: no contest/defense on contract terms. Court enforced the indemnity as written; applied causation test (losses incurred because Developers furnished bonds).
Damages for payments to claimants, consultants, and attorneys Developers: produced checks and affidavit establishing payments totaling $212,566.56 (after $10,000 recoupment). Cercontec: no contest. Court awarded $212,566.56 (payments to claimants and consultants plus attorneys’ fees), finding documentary evidence sufficient—no evidentiary hearing required.
Pre- and post-judgment interest and other costs Developers: requested interest from payment dates and post-judgment interest; sought unspecified additional costs. Cercontec: no contest. Court awarded pre-judgment interest at 12% per annum from payment dates (per contract/Louisiana law) and post-judgment interest under 28 U.S.C. § 1961; declined to award unspecified additional costs for lack of evidence.

Key Cases Cited

  • N.Y. Life Ins. Co. v. Brown, 84 F.3d 137 (5th Cir. 1996) (describing default judgment procedure under Rule 55)
  • Nishimatsu Constr. Co., Ltd. v. Houston Nat. Bank, 515 F.2d 1200 (5th Cir. 1975) (default admits well‑pleaded facts but not legal conclusions)
  • Gray Ins. Co. v. Terry, [citation="606 F. App'x 188"] (5th Cir. 2015) (indemnity causation test: indemnitor liable for losses incurred because surety furnished a bond)
  • Lindsey v. Prive Corp., 161 F.3d 886 (5th Cir. 1998) (factors for determining appropriateness of default judgment)
  • James v. Frame, 6 F.3d 307 (5th Cir. 1993) (default-judgment damages normally require a hearing unless sum is liquidated or mathematically determinable)
  • Richardson v. Salvation Army, S. Territory, USA, 161 F.3d 7 (5th Cir. 1998) (courts may rely on affidavits and documentary evidence to calculate damages on default)
Read the full case

Case Details

Case Name: Developers Surety & Indemnity Co v. Cercontec L L C
Court Name: District Court, W.D. Louisiana
Date Published: Mar 13, 2020
Citation: 5:18-cv-01379
Docket Number: 5:18-cv-01379
Court Abbreviation: W.D. La.