History
  • No items yet
midpage
DeSilva Gates Construction, LP v. Department of Transportation
195 Cal. Rptr. 3d 891
Cal. Ct. App.
2015
Read the full case

Background

  • CalTrans issued an information for bids (IFB) for a $34M highway widening project and issued Addendum #1 changing bid opening date and several plan/bid items; the IFB required contractors to list subcontractors performing >0.5% of the bid (or $10,000) and permitted a 24-hour fax supplement after bid opening.
  • Nine bids were opened: Security (lowest), DeSilva (second-lowest), Papich (third). DeSilva faxed a 24-hour subcontractor list adding All Steel Fence, which was slated to perform ~$15,023 (<< 0.5% of DeSilva’s $31.6M bid).
  • Papich failed to acknowledge Addendum #1 on its bid. CalTrans initially flagged Papich for that omission but allowed Papich to submit proof it considered and agreed to Addendum #1 and later treated Papich’s bid as responsive.
  • CalTrans rejected DeSilva’s bid as nonresponsive on the ground that DeSilva had changed its subcontractor list after bid opening; CalTrans then awarded the contract to Papich.
  • DeSilva petitioned for a writ of mandate; the trial court granted relief, holding DeSilva’s bid was responsive and CalTrans abused its discretion by allowing Papich to cure a material omission. CalTrans and Papich appealed; the appellate court affirmed.

Issues

Issue Plaintiff's Argument (DeSilva) Defendant's Argument (CalTrans/Papich) Held
Whether DeSilva’s bid was nonresponsive because its 24‑hour subcontractor list added a subcontractor not listed in the original bid The 24‑hour list merely provided accurate but unnecessary additional information; All Steel Fence performed <0.1% of the contract and did not trigger the statutory disclosure threshold, so DeSilva’s bid remained responsive CalTrans/Papich argued the change in subcontractor listing after bid opening amounted to an impermissible post‑bid alteration and justified rejection DeSilva’s bid was responsive. Adding a subcontractor who performed less than the statutory threshold did not violate the IFB or Public Contract Code and did not render the bid nonresponsive
Whether CalTrans properly waived Papich’s failure to acknowledge Addendum #1 (a material deviation) Waiver was improper because CalTrans had stated acknowledgment of a material amendment was required and permitting Papich to cure gave Papich an unfair competitive advantage over other bidders CalTrans/Papich argued the agency had discretion to accept documentary proof and cure the omission CalTrans abused its discretion in allowing Papich to cure a material omission; permitting cure conferred an unfair advantage and was unlawful, so Papich’s bid should not have been accepted

Key Cases Cited

  • MCM Construction, Inc. v. City & County of San Francisco, 66 Cal.App.4th 359 (1998) (defines responsive bid as one that promises to do what bidding instructions require)
  • Bay Cities Paving & Grading, Inc. v. City of San Leandro, 223 Cal.App.4th 1181 (2014) (bid responsiveness requires conformity to agency specifications)
  • Ghilotti Construction Co. v. City of Richmond, 45 Cal.App.4th 897 (1996) (standard of review for public contracting awards; review limited to arbitrary/capricious errors)
  • Valley Crest Landscape, Inc. v. City Council, 41 Cal.App.4th 1432 (1996) (agency may not allow cure of material bid element when cure would give unfair advantage)
  • Wilson & Wilson v. City Council of Redwood City, 191 Cal.App.4th 1559 (2011) (mootness and justiciability principles for public works disputes)
Read the full case

Case Details

Case Name: DeSilva Gates Construction, LP v. Department of Transportation
Court Name: California Court of Appeal
Date Published: Dec 14, 2015
Citation: 195 Cal. Rptr. 3d 891
Docket Number: C074521
Court Abbreviation: Cal. Ct. App.