History
  • No items yet
midpage
146 Conn. App. 60
Conn. App. Ct.
2013
Read the full case

Background

  • Design Tech and Moriniere entered a written construction contract (Nov. 16, 2009) to rebuild a residence; contract required written, pre-priced change orders and provided for arbitration and attorney’s fees.
  • During construction the parties agreed to numerous undocumented change orders; work continued without complying with the contract’s written-change-order formalities.
  • Dispute arose after disagreements over extras/credits; Moriniere terminated Design Tech (June 23, 2011). Design Tech sought arbitration claiming ~$67,983; Moriniere counterclaimed ~$150,000.
  • An unrestricted AAA arbitration awarded Design Tech $106,194 (damages, fees, costs, and attorney’s fees), finding (inter alia) that the parties waived/enforced the contract, Design Tech substantially performed, and Moriniere breached by improper termination and nonpayment.
  • Design Tech moved to confirm the award in superior court; Moriniere moved to vacate under Conn. Gen. Stat. § 52-418(a)(4), alleging the arbitrator manifestly disregarded the law in several ways.
  • The trial court confirmed the award; on appeal the Appellate Court affirmed, applying the narrow Garrity/manifest-disregard standard and finding no basis to vacate.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether arbitrator manifestly disregarded law by awarding estimated/unjust enrichment-style damages while finding an enforceable written contract Design Tech: award was based on enforceable contract, waiver/estoppel of written change-order requirement, and contract remedies — not unjust enrichment Moriniere: once written change-order requirement ignored, there was no enforceable bargain on extras so arbitrator improperly used equitable/estimated damages inconsistent with an express contract Held: No manifest disregard — arbitrator found waiver/estoppel, enforced the contract, and did not clearly apply unjust enrichment; mere legal error is insufficient to vacate.
Whether arbitrator erred in finding Moriniere breached by failing to pay a “proper amount” despite no fixed agreed prices for extras Design Tech: parties waived written pricing; Moriniere refused to pay for extras despite acquiescing to work performed Moriniere: lack of pre-agreed prices means he could not be held to pay an unspecified amount Held: No manifest disregard — arbitrator reasonably found waiver/estoppel and that Moriniere failed to pay for extras; record supports award.
Whether arbitrator should have required proof of actual cost as a condition precedent or assessed damages under contract cost-plus formula Design Tech: plaintiff provided change order with prices prior to termination; arbitrator accepted estimates and awarded amounts (including 12% as contract contemplates) Moriniere: article 8.1 required submission of actual cost as condition precedent and 12% fee; arbitrator improperly used estimates/reasonable value Held: No manifest disregard — arbitrator found waiver of the written precondition, credited evidence (including defendant’s expert estimates), and applied contract principles (adding 12%); defendant failed Garrity test.

Key Cases Cited

  • Garrity v. McCaskey, 223 Conn. 1 (1992) (adopts three-part test for vacatur based on manifest disregard of law)
  • AFSCME, Council 4 v. Dept. of Correction, 298 Conn. 824 (2010) (highly deferential review of arbitral awards; manifest-disregard standard rarely met)
  • Teamsters Local Union No. 677 v. Board of Education, 122 Conn. App. 617 (2010) (review principles for unrestricted submissions; courts minimize interference with arbitration)
  • Lathuras v. Shoreline Dental Care, LLC, 65 Conn. App. 509 (2001) (examples of vacatur only where arbitrator knowingly issued an award contrary to law)
Read the full case

Case Details

Case Name: Design Tech, LLC v. Moriniere
Court Name: Connecticut Appellate Court
Date Published: Sep 24, 2013
Citations: 146 Conn. App. 60; 76 A.3d 712; 2013 WL 5274352; 2013 Conn. App. LEXIS 464; AC 34981
Docket Number: AC 34981
Court Abbreviation: Conn. App. Ct.
Log In
    Design Tech, LLC v. Moriniere, 146 Conn. App. 60