AC48336
Conn. App. Ct.Jul 28, 2026Background
- The Department of Administrative Services awarded Bestech and others a hazardous materials abatement contract for state work at the former Bergin Correctional Institution site. 1
- After a April 2021 stop-work order, Bestech left equipment at the site and claimed state representatives repeatedly told it work would resume soon. 2
- Bestech later sought over $1.4 million for idle equipment costs and filed an arbitration demand under General Statutes § 4-61. 3
- The department refused arbitration, asserted sovereign immunity, and sought injunctive relief because the claim did not arise under the contract and the contract barred idle-equipment recovery. 4
- The trial court held § 4-61(a)'s waiver did not apply, granted an injunction, and barred Bestech from arbitrating. 5
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Does § 4-61 waive sovereign immunity for Bestech’s arbitration claim? 6 | Department said the claim did not arise under the contract and was barred. | Bestech said its claim arose under the contract and was arbitrable. | No; the claim fell outside § 4-61(a)'s limited waiver. 7 |
| May the court examine the contract language to decide § 4-61 coverage? 8 | Department said the court must determine waiver before arbitration. | Bestech said the arbitrator, not the court, should decide. | Yes; courts decide sovereign-immunity coverage and may inspect the cited contract language. 9 |
| Did Bestech's idle-equipment theory fall 'under' the contract? 10 | Department said no contract term authorized idle-equipment damages. | Bestech said general payment and breach provisions were enough. | No; the claim was only related to the contract, not directly under it. 11 |
| Did Walter Kidde allow this delay-damages claim? 12 | Department said Walter Kidde was distinguishable. | Bestech said delay damages are recoverable under § 4-61. | No; Walter Kidde was inapposite because this claim rested on oral representations and idle equipment. 13 |
Key Cases Cited
- Himmelstein v. Windsor, 304 Conn. 298 (Conn. 2012) (state immunity is waived only by clear legislative consent 14)
- Dept. of Transportation v. White Oak Corp., 287 Conn. 1 (Conn. 2008) (§ 4-61 is a narrow waiver; arbitration depends on a qualifying claim under subsection (a) 15)
- Dept. of Public Works v. ECAP Construction Co., 250 Conn. 553 (Conn. 1999) ('under' § 4-61 means directly under the contract, not merely related to it 16)
- Sagamore Group, Inc. v. Commissioner of Transportation, 29 Conn. App. 292 (Conn. App. 1992) (claimant must show a precise fit between the statute and the contractual language invoked 17)
- Bacon Construction Co. v. Dept. of Public Works, 294 Conn. 695 (Conn. 2010) (ECAP correctly interprets the scope of § 4-61's sovereign-immunity waiver 18)
- Walter Kidde Constructors, Inc. v. State, 37 Conn. Supp. 50 (Conn. Super. 1981) (recognized certain delay damages in a public-works contract case, but on different facts 19)
