midpage
Sign in to see your projects.
AC48336
Conn. App. Ct.
Jul 28, 2026
Read the full case

Background

  • The Department of Administrative Services awarded Bestech and others a hazardous materials abatement contract for state work at the former Bergin Correctional Institution site. 1
  • After a April 2021 stop-work order, Bestech left equipment at the site and claimed state representatives repeatedly told it work would resume soon. 2
  • Bestech later sought over $1.4 million for idle equipment costs and filed an arbitration demand under General Statutes § 4-61. 3
  • The department refused arbitration, asserted sovereign immunity, and sought injunctive relief because the claim did not arise under the contract and the contract barred idle-equipment recovery. 4
  • The trial court held § 4-61(a)'s waiver did not apply, granted an injunction, and barred Bestech from arbitrating. 5

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does § 4-61 waive sovereign immunity for Bestech’s arbitration claim? 6 Department said the claim did not arise under the contract and was barred. Bestech said its claim arose under the contract and was arbitrable. No; the claim fell outside § 4-61(a)'s limited waiver. 7
May the court examine the contract language to decide § 4-61 coverage? 8 Department said the court must determine waiver before arbitration. Bestech said the arbitrator, not the court, should decide. Yes; courts decide sovereign-immunity coverage and may inspect the cited contract language. 9
Did Bestech's idle-equipment theory fall 'under' the contract? 10 Department said no contract term authorized idle-equipment damages. Bestech said general payment and breach provisions were enough. No; the claim was only related to the contract, not directly under it. 11
Did Walter Kidde allow this delay-damages claim? 12 Department said Walter Kidde was distinguishable. Bestech said delay damages are recoverable under § 4-61. No; Walter Kidde was inapposite because this claim rested on oral representations and idle equipment. 13

Key Cases Cited

  • Himmelstein v. Windsor, 304 Conn. 298 (Conn. 2012) (state immunity is waived only by clear legislative consent 14)
  • Dept. of Transportation v. White Oak Corp., 287 Conn. 1 (Conn. 2008) (§ 4-61 is a narrow waiver; arbitration depends on a qualifying claim under subsection (a) 15)
  • Dept. of Public Works v. ECAP Construction Co., 250 Conn. 553 (Conn. 1999) ('under' § 4-61 means directly under the contract, not merely related to it 16)
  • Sagamore Group, Inc. v. Commissioner of Transportation, 29 Conn. App. 292 (Conn. App. 1992) (claimant must show a precise fit between the statute and the contractual language invoked 17)
  • Bacon Construction Co. v. Dept. of Public Works, 294 Conn. 695 (Conn. 2010) (ECAP correctly interprets the scope of § 4-61's sovereign-immunity waiver 18)
  • Walter Kidde Constructors, Inc. v. State, 37 Conn. Supp. 50 (Conn. Super. 1981) (recognized certain delay damages in a public-works contract case, but on different facts 19)
Read the full case

Case Details

Case Name: Dept. of Administrative Services v. Bestech, Inc. of Connecticut
Court Name: Connecticut Appellate Court
Date Published: Jul 28, 2026
Citation: AC48336
Docket Number: AC48336
Court Abbreviation: Conn. App. Ct.
Log In