History
  • No items yet
midpage
Department of Transportation v. White Oak Corp.
2013 WL 1296776
Conn. App. Ct.
2013
Read the full case

Background

  • Public works contracts allowed arbitration under General Statutes § 4-61 (b) with a narrow sovereign immunity waiver.
  • White Oak pursued two arbitrations (Tomlinson and Bridgeport) against the Department of Transportation (Department).
  • The Tomlinson arbitration panel found no wrongful termination and the trial court confirmed it; White Oak then sought to dismiss/limit the Bridgeport arbitration proceedings.
  • The Connecticut Supreme Court in White Oak I held that the waiver under § 4-61(a) is a matter for courts, and the scope of the arbitral submission under § 4-61(b) is narrow and cannot be expanded by arbitrators.
  • Judge Sheldon’s injunction ruling adopted as law of the case held White Oak’s Bridgeport demand alleged a single wrongful termination claim with a single damages amount, limiting the arbitration scope.
  • The arbitration panel later determined that White Oak’s Bridgeport claim included damages beyond wrongful termination, awarding liquidated damages and prejudgment interest, which the Department sought to vacate; the trial court denied vacatur and confirmed the award.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the arbitration panel exceeded its powers under § 4-61(b). Department argues panel exceeded submission by addressing non‑termination damages. White Oak asserts panel’s rules allowed determination of its own jurisdiction. Yes; panel exceeded submission by ruling on arbitrability beyond termination claim.
Whether the Department waived judicial review of arbitrability. Department never validly consented to panel deciding arbitrability; pursued injunction. White Oak relies on Bacon Construction to claim waiver. No waiver; Department did not consent to arbitrator’s jurisdiction over arbitrability.
Whether law of the case or res judicata bars re‑litigation of arbitrability issues. Judge Sheldon’s law of the case governs arbitrability. Law of the case supports limiting arbitrability to termination. Law of the case applied; however, panel still exceeded authority, so vacatur granted.
What standard of review applies to challenges to arbitrability in this context. De novo review for arbitrability questions. Arbitrability questions are reviewed de novo; interpretation constrained by § 4-61. De novo review governs arbitrability questions.

Key Cases Cited

  • Dept. of Transportation v. White Oak Corp., 287 Conn. 1 (2008) (Supreme Court held sovereign immunity question is for courts, not arbitrators, and bounds on 4-61(b) are narrow.)
  • Bacon Construction Co. v. Dept. of Public Works, 294 Conn. 695 (2010) (Waiver of judicial review of arbitrability requires clear, unequivocal consent to arbitration of arbitrability.)
  • New Britain v. AFSCME, Council 4, Local 1186, 304 Conn. 639 (2012) (De novo review of arbitrability where challenged; contractual scope matters.)
  • Stratford v. International Assn. of Firefighters, AFL-CIO, Local 998, 248 Conn. 108 (1999) (Arbitration review governed by contract scope; restricts judicial intervention.)
  • C.F.M. of Connecticut, Inc. v. Chowdhury, 239 Conn. 375 (1996) (Law of the case; interlocutory rulings can guide later proceedings.)
Read the full case

Case Details

Case Name: Department of Transportation v. White Oak Corp.
Court Name: Connecticut Appellate Court
Date Published: Apr 9, 2013
Citation: 2013 WL 1296776
Docket Number: AC 33458
Court Abbreviation: Conn. App. Ct.