History
  • No items yet
midpage
Department Of Labor And Industries, V. Phillips 66 Company
80685-8
Wash. Ct. App.
Jun 28, 2021
Read the full case

Background

  • Phillips 66 operates a Ferndale refinery with an extensive fire water system (1,000,000‑gallon tank, ponds, hydrants, grid piping, pumps, 30,000+ gpm capacity, redundant water sources).
  • The Department of Labor & Industries inspected the refinery, observed leaks and a leaking hydrant, and cited Phillips 66 for alleged violations of the PSM rules: mechanical integrity (WAC 296‑67‑037) and process hazard analysis (WAC 296‑67‑017).
  • Phillips 66’s written policy inspected above‑ground fire equipment but did not include standards for inspecting underground piping or the interior of the storage tank.
  • The Board and Whatcom County Superior Court concluded the fire water system was not a “process” or “process equipment” under WAC 296‑67 and vacated the citations because the system contains no highly hazardous chemicals.
  • The Court of Appeals reversed: it held the fire water system falls within the PSM definition of “process” and that both the mechanical integrity and PHA regulations apply; it remanded to the Board to determine compliance (including the proper RAGAGEP).
  • Parties disputed compliance specifics: the Department relied on NFPA 25 as RAGAGEP (interior tank inspection required), while Phillips 66 relied on API inspection methods and testimony that its inspections satisfied applicable standards.

Issues

Issue Plaintiff's Argument (Department) Defendant's Argument (Phillips 66) Held
Whether the fire water system is a “process” under the PSM rules The system is involved in activities that mitigate releases of highly hazardous chemicals and thus falls within the PSM definition of “any activity involving” a highly hazardous chemical The fire water system contains no highly hazardous chemicals and is not connected to process equipment, so it is not a PSM‑covered process Held: Fire water system is a “process” under the PSM rules because it mitigates consequences of catastrophic releases and fits the definition’s broad, non‑exhaustive scope
Whether the mechanical integrity regulation (WAC 296‑67‑037) applies to the fire water system The regulation applies to listed process equipment (piping, pumps, tanks, valves) and Appendix C specifically identifies fire protection systems as components for mechanical integrity programs The Board previously treated similar utility components as outside the mechanical integrity scope; Phillips 66 argues its system is not process equipment because it lacks hazardous chemicals Held: Mechanical integrity regulation applies; many fire water components fall within the regulation and Appendix C contemplates including fire protection systems
Whether the process hazard analysis regulation (WAC 296‑67‑017) applies PHAs must address consequences of failure of controls; the fire water system controls hazards and thus must be analyzed Because the system contains no hazardous chemicals, Phillips 66 contends it need not be the subject of PHAs Held: PHA regulation applies because the fire water system is part of a PSM‑covered process and controls hazards at the refinery
Whether Phillips 66 complied with mechanical integrity and PHA requirements (RAGAGEP and adequacy of PHAs) Phillips 66 failed to inspect interior tank and underground piping per NFPA 25 (RAGAGEP); PHAs did not meaningfully analyze fire water system failure Phillips 66 contends it used API inspection methods and certified inspectors and that PHAs considered loss of controls; evidence conflicted Held: Court did not decide compliance; remanded to the Board to determine appropriate RAGAGEP and whether Phillips 66 complied with mechanical integrity and PHA requirements

Key Cases Cited

  • Delek Ref., Ltd. v. Occupational Safety & Health Rev. Comm’n, 845 F.3d 170 (5th Cir. 2016) (federal decision treating a safety/utility unit that mitigates releases as within PSM coverage)
  • Erection Co. v. Dep’t of Labor & Indus., 160 Wn. App. 194 (2011) (standard for reviewing Board decisions under WISHA)
  • Potelco Inc. v. Dep’t of Labor & Indus., 191 Wn. App. 9 (2015) (Washington courts may consult federal OSHA decisions as persuasive authority)
  • Mader v. Health Care Auth., 149 Wn.2d 458 (2003) (interpretation of unambiguous regulations by plain meaning)
  • Schimmick Constr. Co. Inc. v. Dep’t of Labor & Indus., 12 Wn. App. 2d 770 (2020) (deference to Department interpretations and rules on statutory/regulatory construction)
  • Associated Press v. Wash. State Legislature, 194 Wn.2d 915 (2019) (use of “including” as non‑exhaustive list in statutory/ regulatory interpretation)
Read the full case

Case Details

Case Name: Department Of Labor And Industries, V. Phillips 66 Company
Court Name: Court of Appeals of Washington
Date Published: Jun 28, 2021
Docket Number: 80685-8
Court Abbreviation: Wash. Ct. App.