midpage
Projects
Sign in to see your projects.
60 So. 3d 102
La. Ct. App.
2011
Read the full case

Background

  • Talbot and Privat contracted for Talbot to perform site work and concrete on a bank project; privat acted as general contractor.
  • On June 14, 2004, Talbot submitted two proposals totaling $162,000; work began before Talbot was licensed.
  • Talbot did not have a contractor's license when entering the contracts; license obtained August 31, 2004.
  • Talbot signed a lien waiver February 9, 2005, acknowledging work performed and value, while bills remained unpaid to vendors.
  • Privat paid vendors to prevent liens and incurred additional costs to complete Talbot’s work; Talbot later sought payment for remaining balance.
  • Trial court dismissed Talbot’s claims, finding illegal license status and that Privat’s reconventional demand was barred by clean hands; appellate review followed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether lack of license bars Talbot’s recovery Talbot argued Hagberg allows recovery under equity. Privat argued license required; Hagberg distinguishable; no equitable recovery. Talbot not entitled to recovery; license requirement upheld.
Whether Hagberg permits recovery of costs despite no license Hagberg supports recovery of actual costs under unjust enrichment. Hagberg distinguished; not applicable here. Not entitled to recovery under equity/unjust enrichment.
Whether Talbot’s substandard work affects entitlement Talbot argues not dispositive if license obtained; costs recoverable. Substandard work supports denial under Hagberg framework. Court upheld denial based on overall equitable/unenforceable contract concerns.
Whether Privat’s reconventional demand is barred by clean hands N/A Privat’s demand should not be barred; Talbot’s conduct tainted. Alternative issues moot; clean hands not aiding Talbot’s position.
What is the controlling remedy when contract violates licensing statute Equitable recovery should be allowed to compensate actual costs. Maintain statutory licensing protection; no recovery for Talbot. Affirmed trial court; no recovery for Talbot; costs assessed to Talbot.

Key Cases Cited

  • Hagberg v. John Bailey Contractor, 435 So.2d 580 (La.App. 3 Cir.1983) (licensing rules not meant to penalize valid charges when no fraud or substandard work)
  • Boxwell v. Department of Highways, 14 So.2d 627 (La. 1943) (unjust enrichment recovery where contract unenforceable)
Read the full case

Case Details

Case Name: Dennis Talbot Construction Co. v. Privat General Contractors, Inc.
Court Name: Louisiana Court of Appeal
Date Published: Mar 23, 2011
Citations: 60 So. 3d 102; 2011 La. App. LEXIS 342; 10 La.App. 3 Cir. 1300; 2011 WL 1004903; No. 10-1300
Docket Number: No. 10-1300
Court Abbreviation: La. Ct. App.
Log In
    Dennis Talbot Construction Co. v. Privat General Contractors, Inc., 60 So. 3d 102