History
  • No items yet
midpage
DeFoe v. Schoen Builders, L.L.C.
2019 Ohio 2255
Ohio Ct. App.
2019
Read the full case

Background

  • John and Jodie DeFoe contracted with Schoen Builders, LLC (SB) on Jan. 18, 2013 to build a custom home; contract price stated $623,317; they moved in April 2014 and paid > $1.3M overall, with final payment on May 9, 2014.
  • Appellants sued in 2015 and filed a nine-count amended complaint alleging breach of contract, rescission, negligence, breach of warranty, CSPA and various fraud claims; appellees moved for summary judgment on all counts.
  • Trial court granted summary judgment for appellees on Counts 1–5, 7–8 (contract, rescission, negligence, warranties, fraud claims) but denied as to CSPA and NIED; later CSPA was dismissed for lack of standing and NIED was voluntarily dismissed by plaintiffs (but that dismissal was later held improper).
  • Appellants appealed the Feb. 20, 2018 summary-judgment order; the Sixth District considered whether the order was final and then reviewed the merits de novo.
  • Key factual dispute central to several claims: contract paragraph 5 (possession/occupancy before final payment equals acceptance and limits warranty obligations) and whether latent defects, negligent construction, or fraudulent statements exist.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
1. Jurisdiction / final appealable order DeFoe says the Feb. 20, 2018 summary-judgment entry is appealable; Civ.R. 54(B) was entered later. Schoen argues appeal is not from a final order because other claims remained and voluntary dismissal cannot manufacture finality. Court found the Feb. 20 order affected substantial rights and, with Civ.R. 54(B) language entered later, the appeal was properly before the court.
2. Breach of contract & express warranty (para. 5 possession clause) DeFoe: para. 5 ambiguous or unenforceable; moving in before final payment did not waive claims for latent defects; R.C. Chapter 4722 limits such clauses. SB: para. 5 unambiguous — occupancy before payment equals acceptance and relieves contractor of warranty obligations; Kott controls. Court: para. 5 is unambiguous as to "possession"; DeFoes took possession before final payment, so paragraph 5 bars warranty remedies under paragraph 12. Kott remains valid post-R.C. 4722. Result: summary judgment affirmed in part (limited to precluding paragraph-12 warranty remedies).
3. Negligence & implied workmanlike-warranty claims DeFoe: engineering report and testimony create genuine issues of fact that SB breached duties/constructed unworkmanlike. SB: para. 5/acceptance bars further obligations and thus bars negligence/workmanship claims. Court: SB failed to show entitlement to judgment as a matter of law on negligence and implied-warranty/workmanlike claims; genuine issues of material fact remain. Summary judgment reversed as to Counts 3 and 5.
4. Rescission and fraud (fraudulent misrepresentation/fraud) DeFoe: defects, misrepresentations about project management, selections coordinator, quality, and overcharging support rescission and fraud claims. Schoen: plaintiffs did not justifiably rely on alleged statements for contracting; many allegations unproven or speculative. Court: genuine issues of material fact exist on fraud claims (Counts 7–8); rescission (Count 2) cannot be dismissed because related contract/negligence claims remain. Summary judgment reversed as to Counts 2, 7, and 8.

Key Cases Cited

  • Pattison v. W.W. Grainger, Inc., 120 Ohio St.3d 142, 2008-Ohio-5276, 897 N.E.2d 126 (Ohio 2008) (a plaintiff may not create finality by voluntarily dismissing remaining claims after partial adjudication).
  • General Acc. Ins. Co. v. Ins. Co. of N. Am., 44 Ohio St.3d 17, 540 N.E.2d 266 (Ohio 1989) (appellate court jurisdiction requires a final order under R.C. 2505.02).
  • Chef Italiano Corp. v. Kent State Univ., 44 Ohio St.3d 86, 541 N.E.2d 64 (Ohio 1989) (finality requires both R.C. 2505.02 and, when applicable, Civ.R. 54(B)).
  • Kott v. Gleneagles Prof’l Builders & Remodelers, Inc., 197 Ohio App.3d 699, 2012-Ohio-287, 968 N.E.2d 593 (6th Dist.) (occupancy prior to full payment may constitute acceptance and relieve contractor of further obligation under contract terms).
  • Velotta v. Leo Petronzio Landscaping, Inc., 69 Ohio St.2d 376, 433 N.E.2d 147 (Ohio 1982) (distinguishes claims based on already-constructed work from claims arising from future-construction contracts).
  • Kishmarton v. William Bailey Constr., Inc., 93 Ohio St.3d 226, 754 N.E.2d 785 (Ohio 2001) (where a sale includes future construction, the implied duty to build in a workmanlike manner arises from the contract).
Read the full case

Case Details

Case Name: DeFoe v. Schoen Builders, L.L.C.
Court Name: Ohio Court of Appeals
Date Published: Jun 7, 2019
Citation: 2019 Ohio 2255
Docket Number: WD-18-031
Court Abbreviation: Ohio Ct. App.