History
  • No items yet
midpage
DCX-CHOL Enterprises, Inc.
ASBCA No. 58742
| A.S.B.C.A. | Oct 11, 2016
Read the full case

Background

  • Navy awarded Contract No. N00104-05-C-FA80 to DCX-CHOL for submarine "stuffing tubes," classified Level I/SUB SAFE (safety-critical).
  • Bilateral mod P00020 extended remaining delivery date to 15 Feb 2013.
  • DCX missed the 15 Feb 2013 delivery; emails in Feb 2013 discussed supplier delays and an estimated delivery week of March 25, 2013, but no formal extension or consideration was agreed.
  • On 5 Mar 2013 the contracting officer issued a show-cause letter threatening termination for default; DCX replied asserting delays and proposed shipment by 8 May 2013.
  • Contract specialist recommended default termination citing chronic late deliveries and quality issues; CO terminated for default by mod P00021 on 17 Apr 2013.
  • DCX moved for summary judgment seeking conversion of the default termination to a convenience termination based on alleged waiver; the Board denied the motion on 11 Oct 2016.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether government waived right to terminate for default by permitting continued performance after the due date Navy's emails and conduct (notably the 19 Feb exchange) showed forbearance and the Navy knew DCX continued performance, so waiver occurred Navy says there was no forbearance: no agreed extension/consideration, CO promptly issued show-cause, and termination followed; disputed facts preclude waiver finding Denied: DCX did not prove the two De Vito elements (forebearance and known contractor reliance); no waiver shown
Whether there was "forbearance" by the government after the 15 Feb due date DCX relies on contract specialist's 19 Feb email as indicating forbearance Navy points to the 5 Mar show-cause letter that explicitly preserved rights and sought excuses, showing no forbearance Held for Navy: record lacks evidence of circumstances indicating forbearance
Whether DCX continued performance in reliance with government's knowledge and consent DCX claims supplies were manufactured/ready and continued work with Navy awareness Navy notes DCX's communications only projected future ship dates and do not show actual continued performance or Navy consent Held for Navy: insufficient evidence that DCX continued performance with government knowledge/consent
Whether summary judgment was appropriate DCX argues no genuine issue of material fact and is entitled to judgment as a matter of law Navy argues disputed material facts exist and DCX failed to show elements of waiver Held: Summary judgment denied; DCX failed to meet its burden under Rule 56 and controlling precedent

Key Cases Cited

  • De Vito v. United States, 413 F.2d 1147 (Ct. Cl. 1969) (sets two-element test for government waiver of default: forbearance and contractor reliance/continued performance with knowledge)
  • Switlik Parachute Co. v. United States, 573 F.2d 1228 (Ct. Cl. 1978) (addresses scope of forbearance and evidence needed to infer waiver)
  • Celotex Corp. v. Catrett, 477 U.S. 317 (1986) (summary judgment burden-shifting principles)
  • Mingus Constructors, Inc. v. United States, 812 F.2d 1387 (Fed. Cir. 1987) (contractor bears burden to show entitlement to summary judgment in bid/procurement context)
Read the full case

Case Details

Case Name: DCX-CHOL Enterprises, Inc.
Court Name: Armed Services Board of Contract Appeals
Date Published: Oct 11, 2016
Docket Number: ASBCA No. 58742
Court Abbreviation: A.S.B.C.A.