History
  • No items yet
midpage
Davis v. Nicholsen CA1/5
A161594
| Cal. Ct. App. | May 5, 2022
Read the full case

Background

  • Monica Davis owned a parcel with a deeded 20-foot access easement but for years used an existing paved roadway across adjacent property (including land owned by Hamilton Nicholsen and a parcel owned by Kelham Vineyards LLC) to reach Mund Road.
  • Litigation followed (quiet title and related claims); the parties attended mandatory settlement conference and, on October 4–5, 2017, executed a written "Settlement Agreement" describing a 20-foot deeded easement to be amended to a metes-and-bounds description "along the existing right-of-way," cost-splitting, surveyor selection, mutual releases, and court retention under CCP § 664.6.
  • Paragraph 8 required selection of a surveyor to complete a lot line adjustment; paragraph 11 required signing a final full-form settlement consistent with the terms. The parties filed a notice of settlement on October 6, 2017.
  • After delays and disputes (including Davis’s refusal to cooperate in designating a surveyor), the trial court ordered Davis to retain a surveyor; Albion Surveys was retained, a merger of the Kelham parcel was done, defendant paid substantial fees, and the lot line adjustment was recorded in February 2020.
  • Nicholsen moved to enforce the October 2017 Agreement under CCP § 664.6 when Davis refused to sign the final form; the trial court found a meeting of the minds and entered judgment enforcing the agreement. Davis appealed, arguing lack of an enforceable agreement and that the judgment impermissibly altered settlement terms.

Issues

Issue Plaintiff's Argument (Davis) Defendant's Argument (Nicholsen) Held
Enforceability under CCP § 664.6 — meeting of the minds and certainty of material terms No meeting of minds; key term (location of new easement) was never agreed and agreement was an "agreement to agree" Agreement specified a 20‑ft easement "along the existing right‑of‑way," parties and surveyor acted under that procedure, so terms were sufficiently definite and performed Court: Substantial evidence showed parties agreed that the new easement would follow the existing paved roadway; the settlement was enforceable under § 664.6
Whether the agreement was unenforceable because a final, formal document was never signed Paragraph 11 required a final full‑form binding agreement, so the October document was incomplete The parties’ written settlement plus their conduct (selection/retention of surveyor, lot line work, payments) manifested intent to be bound despite later formalization Court: The presence of a later formalization clause did not negate the enforceable contract; conduct and written terms were sufficient
Whether the judgment impermissibly altered settlement terms by incorporating exhibits (map/legal description) Judgment’s Exhibit C (map) imposed a boundary Davis had not agreed to and therefore altered the settlement Exhibits merely implemented the agreed procedure (survey and metes-and-bounds description) and reflected the parties’ agreed location Court: Incorporation of the survey map and recorded legal description implemented—not added to—settlement terms and was permissible under § 664.6

Key Cases Cited

  • Skulnick v. Roberts Express, Inc., 2 Cal.App.4th 884 (1992) (trial court may enter judgment enforcing a written settlement under § 664.6 and interpret settlement terms)
  • Weddington Prods., Inc. v. Flick, 60 Cal.App.4th 793 (1998) (settlement agreements are contracts; courts may not add material terms but can interpret parties' agreement)
  • In re Marriage of Assemi, 7 Cal.4th 896 (1994) (trial court assesses certainty of material terms and whether parties expressly agreed to be bound when enforcing settlements)
  • Corkland v. Boscoe, 156 Cal.App.3d 989 (1984) (trial court may consider declarations and oral testimony in § 664.6 proceedings)
  • Pope v. Babick, 229 Cal.App.4th 1238 (2014) (on appeal, record must be considered in full; appellant bears burden to show lack of substantial evidence)
  • Okun v. Morton, 203 Cal.App.3d 805 (1988) (upholding enforcement where parties acted in strict accord with settlement provisions despite disputes)
  • Harris v. Rudin, Richman & Appel, 74 Cal.App.4th 299 (1999) (a later formal writing requirement does not necessarily negate an earlier enforceable agreement)
Read the full case

Case Details

Case Name: Davis v. Nicholsen CA1/5
Court Name: California Court of Appeal
Date Published: May 5, 2022
Docket Number: A161594
Court Abbreviation: Cal. Ct. App.