History
  • No items yet
midpage
959 N.E.2d 369
Ind. Ct. App.
2012
Read the full case

Background

  • Feb 9, 2004, City accepted bids for McGrew Sanitation Area project; Dave's Excavating was lowest bidder and contract executed March 5, 2004 with Liberty Mutual as performance bond guarantor.
  • Dave's requested change orders; June 17, 2004 Dave's notified differing subsurface conditions per section 4.03; June 22 sought price increase; engineer began review.
  • July 6, 2004 engineer advised Dave's to resume work and reviewed claim under 4.03; Dave's refused to recommence pending resolution, alleging breach by City.
  • July 15, 2004 engineer notified City considering default; August 9, 2004 City declared Dave's in default and terminated; August 16, 2004 City awarded completion contract to Eagle Valley, finishing December 16, 2004.
  • March 25, 2005 City demanded payment under performance bond; January 6, 2006 City filed suit against Dave's and Liberty Mutual; Eagle Valley completed project ahead of schedule; City mitigated damages by replacing contractor.
  • After litigation, trial court granted partial summary judgment for City on liability and damages; this appeal followed, with issues on contract liability, bond liability, and attorney’s fees.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Contract liability for Dave's breach Dave's breached 4.03 by not resuming work after notice City breached by failing to investigate/adjust or misapplied 4.03 Dave's breached; City not liable under 4.03; summary judgment for City affirmed
Bond liability for Liberty Mutual City improperly constrained Liberty Mutual's mitigation rights under bond City timely mitigated; Liberty Mutual failed to mitigate promptly Liberty Mutual liable as surety; City properly mitigated and asserted bond rights; trial court affirmed
Attorneys' fees under contract City failed to submit fees as a 'claim' to engineer under 15.02 Attorney's fees not subject to claim/change-order procedures City entitled to attorney's fees; contract procedures do not apply to fee requests; affirmed
Precedent defenses (waiver/condition precedent) Paden barrier applies to failure to satisfy condition precedent No preservation of such defenses; factual distinctions Court rejected as to merits; distinguishing Paden; no reversal based on that defense

Key Cases Cited

  • Rogier v. American Testing & Eng'g Corp., 734 N.E.2d 606 (Ind. Ct. App. 2000) (breach and subsequent remedies interplay under contract terms)
  • Whitaker v. Brunner, 814 N.E.2d 288 (Ind. Ct. App. 2004) (contract interpretation when unambiguous; intent from four corners)
  • Weigand Constr. Co. v. Stephens Fabrication, Inc., 929 N.E.2d 220 (Ind. Ct. App. 2010) (timeliness of claims; cessation-of-work provisions vs. fee claims)
  • Town of Plainfield v. Paden Eng'g Co., 943 N.E.2d 904 (Ind. Ct. App. 2011) (condition precedent and contract termination impact; waiver analysis)
Read the full case

Case Details

Case Name: Dave's Excavating, Inc. v. City of New Castle
Court Name: Indiana Court of Appeals
Date Published: Jan 11, 2012
Citations: 959 N.E.2d 369; 2012 WL 77641; 2012 Ind. App. LEXIS 6; 33A04-1104-PL-199
Docket Number: 33A04-1104-PL-199
Court Abbreviation: Ind. Ct. App.
Log In
    Dave's Excavating, Inc. v. City of New Castle, 959 N.E.2d 369