History
  • No items yet
midpage
7 N.W.3d 868
Neb.
2024
Read the full case

Background

  • D&M Roofing and Siding, Inc. (D&M) sued Distribution, Inc. (Distribution) for breach of contract after Distribution used another contractor for roof repairs.
  • The contract included a 'cancellation fee' provision: if Distribution did not engage D&M for the work, it would pay D&M 20% of the amount paid by the insurer for the work done by D&M.
  • D&M initially limited its claimed damages to the 20% cancellation fee, conceding this in summary judgment proceedings, but later attempted to claim lost profits as an alternative measure.
  • The district court found a valid contract, found a breach, but ruled D&M was not entitled to the cancellation fee because it had performed no work; the unjust enrichment claim was dismissed.
  • The court did not expressly dismiss the breach of contract claim or the entire action in its written orders.
  • D&M appealed, but the Nebraska Supreme Court held no final judgment had been entered and thus dismissed the appeal for lack of jurisdiction.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a final, appealable judgment existed Later order (June 12) was the final judgment; appeal timely December 21 order was the final judgment; no timely appeal filed No final judgment rendered; no appellate jurisdiction
Measure of damages for breach of contract Entitled to lost profits despite prior admissions D&M is limited to contract’s cancellation fee provision Court held D&M bound by its admission; no damages
Effect of judicial admissions during summary judgment Prior admissions do not preclude alternative damages D&M is bound by its own formal admissions throughout litigation Court treated D&M’s prior statements as binding
Necessity of explicit dismissal to end the action Action was still pending due to lack of express dismissal Effectively, all claims were resolved; nothing left to decide Express grant/denial of all relief required

Key Cases Cited

  • Mathiesen v. Kellogg, 315 Neb. 840 (explains finality requirements for appellate review)
  • State v. Parmar, 255 Neb. 356 (statutory compliance for appellate jurisdiction)
  • Paxton v. Paxton, 314 Neb. 197 (final, appealable judgment standard)
  • Tegra Corp. v. Boeshart, 311 Neb. 783 (defines actions vs. special proceedings)
  • Florence Lake Investments v. Berg, 312 Neb. 183 (judgments and final orders are mutually exclusive)
Read the full case

Case Details

Case Name: D&M Roofing & Siding v. Distribution, Inc.
Court Name: Nebraska Supreme Court
Date Published: Jun 28, 2024
Citations: 7 N.W.3d 868; 316 Neb. 952; S-23-516
Docket Number: S-23-516
Court Abbreviation: Neb.
Log In
    D&M Roofing & Siding v. Distribution, Inc., 7 N.W.3d 868