Cutler Associates, Inc. v. Palace Construction
4:15-cv-40021
D. Mass.Sep 22, 2015Background
- Cutler Associates (MA) contracted as design-builder for Mount Ida College's New Hall (2007); Cutler subcontracted exterior sheathing work to Palace/Colby (2007 subcontract contained arbitration and indemnity clauses).
- Construction completed in 2008; Mount Ida notified Cutler of alleged exterior sheathing defects and sought at least $640,000 in damages in 2014.
- Cutler sued Palace/Colby, PCI, and Optimum in MA Superior Court on July 3, 2014; initial service deadline missed, case dismissed without prejudice, then state court extended time and defendants were served in January 2015.
- Mount Ida filed a demand for arbitration (January 2015); Cutler moved to add defendants and then moved in federal court to stay and compel arbitration after removal; defendants moved to dismiss for insufficient service and failure to state a claim.
- The subcontract’s dispute-resolution clause required CEO-level site meeting, mediation, then AAA arbitration for most disputes (with carveout for >$80,000 requiring Cutler’s consent).
- District court denied dismissal for deficient service (deferring to state court extension), stayed merits dismissal, and granted Cutler’s motion to stay the action and compel arbitration.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether service was untimely and warrants dismissal | State court properly extended time; service now effective | Plaintiff failed to serve within 90 days; dismissal required | Denied as to service; district court honored state-court extension and refused to overturn it |
| Whether claims must be arbitrated (existence/scope) | Subcontract broadly covers "all claims relating to this Subcontract," so dispute is arbitrable | Arbitration steps refer to an on-site meeting during construction; clause should be limited to disputes arising during construction | Granted: arbitrability (including scope) is for arbitrator where clause is broad; court compels arbitration |
| Whether preconditions (CEO meeting, mediation) were satisfied | Even if preconditions weren't met, whether they were satisfied is for the arbitrator | Preconditions not met, so dispute not arbitrable | Court found challenges to preconditions presumptively for arbitrator and did not bar arbitration |
| Whether Cutler waived right to arbitrate by litigation conduct | Minimal litigation occurred; moving to compel arbitration was timely; no substantial prejudice | Delay and prior litigation conduct constitute waiver and prejudice (including potential tolling/statute-of-repose issues for third-party claims) | No waiver: court found little litigation activity, minimal prejudice, and thus compelled arbitration |
Key Cases Cited
- Ashcroft v. Iqbal, 556 U.S. 662 (2009) (plausibility standard for Rule 12(b)(6))
- Bell Atl. Corp. v. Twombly, 550 U.S. 544 (2007) (pleading must be plausible, not merely conceivable)
- Howsam v. Dean Witter Reynolds, 537 U.S. 79 (2002) (procedural gateway questions about arbitration presumptively for arbitrator)
- Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1 (1983) (federal policy strongly favors arbitration)
- AT&T Techs., Inc. v. Communs. Workers of Am., 475 U.S. 643 (1986) (ambiguities in arbitration clauses resolved in favor of arbitration absent clear exclusion)
- Grand Wireless, Inc. v. Verizon Wireless, Inc., 748 F.3d 1 (1st Cir. 2014) (apply ordinary contract principles to arbitration clauses; resolve scope ambiguities for arbitration)
- Marie v. Allied Home Mortg. Corp., 402 F.3d 1 (1st Cir. 2005) (waiver/default analysis under FAA; litigation conduct may waive arbitration but burden to show prejudice rests on opposing party)
