History
  • No items yet
midpage
61 A.3d 91
Md. Ct. Spec. App.
2013
Read the full case

Background

  • Cuesport Properties sold Unit 4 to Critical Developments; seller to build a demising wall within 30 days at sole cost.
  • Wall was completed on time but built without a building permit and violated county code.
  • Critical Developments later had the wall modified to meet code; ~260 days elapsed from deadline to completion of modifications.
  • $20,000 escrow was set aside for wall work and any liquidated damages; funds to be used for related costs.
  • Trial court awarded Critical Developments $32,760 in liquidated damages plus $10,443.74 in attorneys’ fees; court treated the per‑diem as liquidated damages and acknowledged partial harmlessness of electrical delay.
  • Electrical service was not timely completed and permit issues contributed to delays; occupancy permit for Unit 4 issued August 28, 2009.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Liquidated damages vs. penalty Cuesport argues the clause is a penalty. Critical Developments contends it is lawful liquidated damages. Valid liquidated damages clause; not a penalty.
Awarding damages under per‑diem clause Damages for delay may be improper if the wall was completed within the period. Court can award per‑diem liquidated damages; not duplicative of other losses. Per‑diem damages upheld for 260 days.
Equitable considerations in damages Equitable factors should reduce or negate some damages due to delay. No duty to mitigate under Barrie School; damages are appropriate. Trial court’s equitable considerations upheld; no error in damages.

Key Cases Cited

  • Traylor v. Grafton, 273 Md. 649, 332 A.2d 651 (Md. 1975) (defining liquidated damages and permissible constraints)
  • Barrie School v. Patch, 401 Md. 497, 933 A.2d 382 (Md. 2007) (test for determining penalty vs. liquidated damages; reasonableness and proportionality)
  • Janusz v. Gilliam, 404 Md. 524, 947 A.2d 560 (Md. 2008) (mutual mistake not grounds to rescind in sophisticated, arms-length deal)
  • City of Boston v. New England Sales & Mfg. Corp., 386 Mass. 820, 438 N.E.2d 68 (Mass. 1982) (per diem damages limited to reasonable time to complete via substitute or owner’s efforts)
  • Oregon State Highway Comm’n v. DeLong Corp., 9 Or. App. 550, 495 P.2d 1215 (Or. App. 1972) (context for per diem liquidated damages and completion timelines)
Read the full case

Case Details

Case Name: Cuesport Properties, LLC v. Critical Developments, LLC
Court Name: Court of Special Appeals of Maryland
Date Published: Feb 27, 2013
Citations: 61 A.3d 91; 2013 WL 706902; 209 Md. App. 607; 2013 Md. App. LEXIS 12; No. 2752
Docket Number: No. 2752
Court Abbreviation: Md. Ct. Spec. App.
Log In
    Cuesport Properties, LLC v. Critical Developments, LLC, 61 A.3d 91