History
  • No items yet
midpage
47 Cal.App.5th 940
Cal. Ct. App.
2020
Read the full case

Background:

  • North Edwards Water District awarded a public-works contract to Clark Bros.; Clark subcontracted Crosno Construction to fabricate, erect, and coat two large steel water tanks for $630,000.
  • The subcontract included a "pay-when-paid" clause requiring Clark to pay subcontractor within a "reasonable time," defined to be at least the time Clark and Crosno need to pursue to conclusion their legal remedies against the owner.
  • A dispute between Clark and the District halted the project after Crosno performed most work; Crosno filed a stop payment notice and then a payment-bond claim against the surety, Travelers, for $562,435 unpaid.
  • Travelers denied the bond claim as premature, invoking the subcontract's pay-when-paid clause to delay payment until Clark’s litigation with the District concluded.
  • Trial court granted summary judgment for Crosno, holding the subcontract clause un enforceable as an unlawful impairment of payment-bond rights under Cal. Civ. Code § 8122 (and related statutes), and awarded principal, prejudgment interest, and fees; Travelers appealed.

Issues:

Issue Plaintiff's Argument (Crosno) Defendant's Argument (Travelers) Held
May a surety invoke an expansive pay-when-paid subcontract clause to delay payment-bond recovery until contractor’s suit against the owner concludes? Clause is void as it "affects or impairs" statutory bond rights under § 8122 unless waived by a valid waiver-and-release tied to payment. Clause only fixes timing (a pay-when-paid), not a waiver; surety may assert principal's defenses—no bond liability until contractor is paid. No. The specific clause is unenforceable against a bond claimant because it unreasonably postpones bond recovery and impairs statutory rights.
Does § 8122 prohibit contractual terms that merely "affect or impair" bond remedies (not only explicit waivers)? § 8122 covers provisions that affect or impair claims; broad protection prevents indirect circumvention of anti-waiver scheme. § 8122 aims at actual waivers; ordinary timing provisions should not be swept in. Court reads § 8122 broadly: provisions that unreasonably affect or impair recovery are void without statutory waiver/payment.
Is a surety's obligation coextensive with the principal’s such that the surety can replicate all subcontract defenses? Bond liability is independent; surety cannot use subcontract terms to narrow bond remedy in ways that would be unlawful if placed in the bond. Surety may assert defenses coextensive with principal’s obligations; freedom of contract should be respected. Bond is statutory and remedial; surety cannot avoid liability by enforcing subcontract terms that impair bond rights (Wm. R. Clarke controlling).
Did the court properly award prejudgment interest and postjudgment fees? Claim was filed and denied by surety; plaintiff seeks statutory prejudgment interest from bond claim notice date and fees allowed by bond statute. Travelers did not raise a separate challenge on fees/interest on appeal. Award of prejudgment interest and attorney’s fees affirmed.

Key Cases Cited

  • Wm. R. Clarke Corp. v. Safeco Ins. Co., 15 Cal.4th 882 (Cal. 1997) (pay-if-paid clauses that effectively waive lien/bond rights are unenforceable; bond liability is independent of subcontract conditional-payment clauses)
  • Yamanishi v. Bleily & Collishaw, Inc., 29 Cal.App.3d 457 (Cal. Ct. App. 1972) (a subcontract clause that indefinitely delays payment until resolution of contractor-owner dispute is unreasonable; subcontractor entitled to payment within a reasonable time)
  • Capitol Steel Fabricators, Inc. v. Mega Const. Co., 58 Cal.App.4th 1049 (Cal. Ct. App. 1997) (pay-if-paid clauses on public works that condition subcontractor payment on governmental payment are void as against public policy)
  • Cooley v. Freeman, 204 Cal. 59 (Cal. 1928) (public-works payment bonds provide subcontractors a quick and sufficient means of payment)
  • Pneucrete Corp. v. U.S. Fid. & Guarantee Co., 7 Cal.App.2d 733 (Cal. Ct. App. 1935) (arbitration or other contractual clauses will not be applied so as to defeat statutory bond remedies)
  • Los Angeles Stone Co. v. National Surety Co., 178 Cal. 247 (Cal. 1918) (surety’s obligation on payment bond is independent of contract deadlines or conditions in the prime contract)
  • United States ex rel. Walton Technol., Inc. v. Weststar Eng’g, Inc., 290 F.3d 1199 (9th Cir. 2002) (federal Miller Act cases refuse to allow pay-when-paid clauses to bar prompt bond recovery; such clauses can effect an impermissible waiver)
Read the full case

Case Details

Case Name: Crosno Construction, Inc. v. Travelers Casualty etc.
Court Name: California Court of Appeal
Date Published: Apr 17, 2020
Citations: 47 Cal.App.5th 940; 261 Cal.Rptr.3d 317; D075561
Docket Number: D075561
Court Abbreviation: Cal. Ct. App.
Log In