History
  • No items yet
midpage
905 N.W.2d 768
N.D.
2018
Read the full case

Background

  • The North Dakota Industrial Commission issued a pooling order for a Billings County spacing unit; Counce (non‑operating working interest owner) elected to participate in Continental’s well and agreed to pay its share of the "reasonable actual cost" of drilling and supervision per N.D.C.C. § 38‑08‑08(2).
  • Continental billed monthly; Counce paid through May 2012 but stopped paying in June 2012, after having already paid amounts that exceeded the AFE estimate.
  • Continental filed an oil and gas production lien and sued to foreclose, claiming about $180,419.12 owed; Counce counterclaimed challenging the reasonableness of charges and asserting various tort claims.
  • While litigation was pending Continental audited the billing, credited Counce $23,573.23, released the lien, and dropped the foreclosure action; Continental then amended its complaint to assert breach of contract and related claims to recover unpaid drilling/operation costs.
  • The district court excluded evidence and dismissed the parties’ claims relating to "reasonable actual cost" by concluding that determination was within the Commission’s exclusive jurisdiction; at trial a jury found Counce breached and awarded Continental $153,666.50.
  • The Supreme Court held the district court lacked subject matter jurisdiction because N.D.C.C. § 38‑08‑08(2) vests exclusive authority in the Industrial Commission to resolve disputes over "reasonable actual cost," and the parties had not exhausted administrative remedies; the judgment was vacated.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether district court had subject‑matter jurisdiction to adjudicate Continental’s breach‑of‑contract claim for unpaid drilling/operation costs Continental: after releasing lien and amending complaint, it could sue in court to collect unpaid amounts Counce: statutory scheme gives the Industrial Commission exclusive authority to determine any dispute over "reasonable actual cost," so parties must exhaust administrative remedies Held: No jurisdiction; statute requires Commission determination of "reasonable actual cost," so court action was improper and judgment vacated
Whether district court had jurisdiction over Counce’s counterclaims challenging the reasonableness of charges Continental: counterclaims are just defenses/claims in the court action Counce: counterclaims necessarily require Commission’s exclusive determination of costs and thus are barred in court without exhaustion Held: No jurisdiction; counterclaims intertwined with Commission’s exclusive subject matter and must be addressed administratively

Key Cases Cited

  • Gadeco, LLC v. Industrial Commission, 812 N.W.2d 405 (N.D. 2012) (background on participating and nonparticipating working interest owners under pooling orders)
  • GEM Razorback, LLC v. Zenergy, Inc., 890 N.W.2d 544 (N.D. 2017) (failure to exhaust administrative remedies can divest court of jurisdiction)
  • Interest of M.W., 785 N.W.2d 211 (N.D. 2010) (subject matter jurisdiction requirement and voidness of judgments entered without it)
  • Brown v. Burleigh County Housing Authority, 833 N.W.2d 512 (N.D. 2013) (judgment entered without subject matter jurisdiction is void and may be vacated)
Read the full case

Case Details

Case Name: Continental Resources, Inc. v. Counce Energy BC 1, LLC
Court Name: North Dakota Supreme Court
Date Published: Jan 22, 2018
Citations: 905 N.W.2d 768; 2018 ND 10; 20170066
Docket Number: 20170066
Court Abbreviation: N.D.
Log In