History
  • No items yet
midpage
Contango Operators, Inc. v. United States
965 F. Supp. 2d 791
S.D. Tex.
2013
Read the full case

Background

  • Contango’s subsea natural-gas pipeline (Atchafalaya channel) was completed in 2008; Contango provided as-built drawings to several federal agencies but not to the Army Corps’ Waterways Division.
  • The Corps solicited and awarded an Atchafalaya-channel dredging contract in 2009; contract specifications listed five pipelines but omitted Contango’s pipeline; Weeks Marine won the contract and began dredging.
  • NOAA updated nautical charts to show Contango’s pipeline (published Nov.–Dec. 2009) and the Coast Guard issued Local Notice to Mariners (LNM 48/09) after Weeks had already commenced work.
  • On Feb. 24, 2010 Weeks Marine’s non‑self‑propelled dredge (G.D. MORGAN) struck and ruptured the Contango pipeline; Contango sued Weeks Marine and the United States in admiralty under the SAA.
  • Procedural posture: multiple cross-motions for summary judgment (liability, government-contractor defense, presumption of fault, res judicata/collateral estoppel) and Weeks Marine’s motion for reconsideration of earlier dismissal of its cross-claim under the Contract Disputes Act (CDA).

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether court should reconsider dismissal of Weeks Marine’s cross-claim under the CDA Reconsideration appropriate; CDA inapplicable to cross-claims CDA applies and divests district court of jurisdiction over contract-based cross-claim Denied — CDA applies; cross-claim falls under administrative submission requirement and district court lacks jurisdiction now (Weeks may pursue administrative route)
United States’ duty and liability for omission of pipeline from contract specs Corps had continuing duty to warn contractor of hazards; omission made accident foreseeable Duty discharged by publishing updated NOAA charts and LNM; Weeks Marine failed to consult them Fact issues preclude summary judgment — scope (duty to warn) exists but whether notice reached Weeks or was sufficient is disputed
Weeks Marine’s negligence / reliance on contract specs Weeks breached duty by failing to investigate or use updated charts/LNMs; over‑dredging alleged Dredger reasonably relied on Corps’ specifications per precedent; not required to independently verify Denied — genuine disputes of material fact (whether reliance was reasonable, industry practice re: charts/LNMs, and whether over‑dredging occurred)
Presumption of fault from allision (non‑self‑propelled vessel vs stationary object) Contango: presumption applies and Weeks cannot rebut Weeks: either presumption inapplicable or rebutted by due care evidence Denied — factual disputes as to Weeks’ knowledge and due care; presumption and rebuttal are triable issues
Government-contractor (sovereign immunity) defense for Weeks N/A (Weeks asserts defense) Weeks: entitled to immunity because acting pursuant to government contract Denied — genuine issues whether U.S. is immune and whether Weeks exceeded authority or acted negligently
Preclusion (res judicata / collateral estoppel) re: Contango’s fault from prior Louisiana judgment Contango: prior judgment forecloses defendants’ comparative‑negligence defenses Defendants: prior judgment resolved different issues (notice/marking), not the specific facts now alleged Denied — res judicata inapplicable to affirmative defenses; collateral estoppel not shown because issues and necessary findings differ

Key Cases Cited

  • De Bardeleben Marine Corp. v. United States, 451 F.2d 140 (5th Cir. 1971) (government duty as cartographer — duty may be discharged once prudent navigator would have received corrected chart/LNM)
  • Michigan Wisconsin Pipeline v. Williams-McWilliams, 551 F.2d 945 (5th Cir. 1977) (Corps’ routine practice of depicting structures may create reliance and duty to show pipelines in contract specs)
  • Southern Natural Gas Co. v. Pontchartrain Materials, Inc., 711 F.2d 1251 (5th Cir. 1983) (Corps’ omission can create duty to prohibit or warn when dredging conflicts with pipelines)
  • Trevino v. Gen. Dynamics Corp., 865 F.2d 1474 (5th Cir. 1989) (claims based on government contracts fall under CDA and must be submitted to contracting officer)
  • Bethlehem Steel Corp. v. Avondale Shipyards, Inc., 951 F.2d 92 (5th Cir. 1992) (district court may hear appeals from administrative determinations under contract dispute procedures)
  • In re Great Lakes Dredge & Dock Co. LLC, 624 F.3d 201 (5th Cir. 2010) (scope of duty in admiralty tied to foreseeability of harm)
  • Ackerson v. Bean Dredging LLC, 589 F.3d 196 (5th Cir. 2009) (government-contractor immunity/Yearsley analysis—contractor not immune if harmed by contractor’s own negligence)
  • Yearsley v. W.A. Ross Constr. Co., 309 U.S. 18 (U.S. 1940) (contractor immunity when authority validly conferred and contractor did not exceed authority)
Read the full case

Case Details

Case Name: Contango Operators, Inc. v. United States
Court Name: District Court, S.D. Texas
Date Published: Aug 15, 2013
Citation: 965 F. Supp. 2d 791
Docket Number: Civil Action No. H-11-0532
Court Abbreviation: S.D. Tex.