History
  • No items yet
midpage
236 A.3d 193
Vt.
2020
Read the full case

Background

  • ECI contracted to rebuild a railroad bridge and subcontracted micropile drilling to CDI, who bid a flat $266,600 price and had prior micropile experience.
  • CDI’s bid included an “additional items” clause: if “drilling in obstructions” (e.g., boulders) required more than 4 hours, payment would be $920 per rig hour plus bit costs; the subcontract separately required formal Change Orders for "changes in the work" and incorporated ECI’s contract with the town.
  • CDI began pile NC-8; after pausing work the casing became stuck. CDI spent 19 days attempting to free it (side hole drilling, jacking) and later billed ECI about $120,000, but did not submit a formal change-order request or written notice asserting a differing subsurface condition.
  • The trial court found the stuck casing was caused by boulders (i.e., obstruction drilling occurred) but held CDI was required to submit a formal change order before billing; it denied CDI’s motions to reopen the evidence / for a new trial and awarded ECI $234,320 in attorneys’ fees under the Prompt Pay Act.
  • CDI appealed (challenging the change-order requirement, denial of reopening/new trial, and fee award); ECI cross-appealed on an evidentiary issue the Court did not reach because it affirmed on the merits.

Issues

Issue Plaintiff's Argument (CDI) Defendant's Argument (ECI) Held
Whether CDI could bill for "drilling in obstructions" without a Change Order The additional-items clause unambiguously entitled CDI to the $920/hr payment when obstruction drilling exceeded 4 hours, without prior notice or Change Order. The subcontract’s Change-Order clause (and incorporation of town contract) makes obstruction drilling a "change in the work" requiring a formal written Change Order before billing. Held for ECI: harmonizing the subcontract, the additional-items pricing is available but must be invoked through the subcontract’s Change-Order process.
Whether denying CDI’s motion to reopen evidence / for a new trial (foreman testimony) was an abuse of discretion Foreman would testify to on-site statements and provide foundation for records; CDI exercised due diligence to locate him. The contract requires formal documentation for Change Orders; informal site conversations would not satisfy the contractual change-order requirements. Held for ECI: no abuse of discretion—proffered testimony could not change outcome because formal written Change-Order documentation was required.
Whether the Prompt Pay Act attorneys’ fee award ($234,320) was unreasonable The fee is disproportionate to case value and reflects unreasonable duplication of two attorneys doing the same work. Fees are reasonable given the case complexity, specialization, and document-intensive litigation; some duplication is acceptable. Held for ECI: trial court did not abuse discretion; it reduced for some duplication but reasonably awarded fees despite exceeding damages.
ECI cross-appeal: admission of CDI owner’s opinion testimony absent Rule 702 reliability finding N/A Owner’s opinion testimony was not proven reliable and should have been excluded; if admitted improperly, new trial is required. Not reached: Court affirmed on merits and declined to address the cross-appeal.

Key Cases Cited

  • John A. Russell Corp. v. Bohlig, 739 A.2d 1212 (interpretation of contracts; harmonize whole instrument and give effect to all parts)
  • Isbrandtsen v. N. Branch Corp., 556 A.2d 81 (language is not ambiguous merely because parties dispute interpretation; contract fairly admitting only one meaning is not ambiguous)
  • Downtown Barre Dev. v. C & S Wholesale Grocers, Inc., 857 A.2d 263 (courts will not insert vaguely implied conditions inconsistent with express contract language)
  • Carmichael v. Adirondack Bottled Gas Corp. of Vt., 635 A.2d 1211 (implied covenant of good faith and fair dealing—party must not undermine other’s contractual benefits)
  • In re Stacy, 411 A.2d 1359 (terms may be read into a contract only when arising by necessary implication)
  • Spooner v. Town of Topsham, 9 A.3d 672 (attorney-fee awards may reduce hours for unreasonable duplication; multiple lawyers OK if distinct contributions shown)
  • Walsh v. Cluba, 117 A.3d 798 (attorney-fee awards can reasonably exceed the damages award if justified by case demands)
  • Afro-American Patrolmen’s League v. City of Atlanta, 817 F.2d 719 (time billed by multiple attorneys recoverable where each made distinct contributions)
Read the full case

Case Details

Case Name: Construction Drilling, Inc. v. Engineers Construction, Inc.
Court Name: Supreme Court of Vermont
Date Published: May 29, 2020
Citations: 236 A.3d 193; 2020 VT 38; 2019-096, 2019-205
Docket Number: 2019-096, 2019-205
Court Abbreviation: Vt.
Log In
    Construction Drilling, Inc. v. Engineers Construction, Inc., 236 A.3d 193