History
  • No items yet
midpage
Conservation Congress v. Nancy Finley
774 F.3d 611
9th Cir.
2014
Read the full case

Background

  • The Beaverslide Project: a Forest Service thinning, fuel-reduction, and timber-supply project on ~13,241 acres in Trinity County, CA; aims to reduce wildfire risk and provide sustainable timber.
  • The Northern Spotted Owl is a ESA-listed threatened species; FWS issued Recovery Plans in 2008 and a revised plan in 2011 with recommended management actions.
  • Forest Service prepared a Biological Assessment (2009), Amendment #1 (2010), and EIS/Supplemental EIS; FWS issued concurrence/technical letters concluding the project was “may affect, not likely to adversely affect” the owl; later (post‑2012) FWS issued a Biological Opinion after critical-habitat redesignation.
  • Conservation Congress sent ESA 60-day notices (2011), sued alleging failures to reinitiate consultation, failure to use best available science (including 2011 Recovery Plan), and NEPA violations; district court granted summary judgment to the agencies; Conservation Congress appealed.
  • The Ninth Circuit reviews de novo and applies the Administrative Procedure Act arbitrary-and-capricious standard, with deference on scientific judgments.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Adequacy of ESA 60‑day notice / jurisdiction Notice failed to specify claims about short‑term effects and Recovery Plan information, so jurisdiction lacking Notices were sufficient; district court had jurisdiction Court: Notice was adequate to confer jurisdiction; plaintiffs need not spell out every legal theory
Mootness after post‑2012 consultation New consultation (and Biological Opinion) moots claims because agencies used 2011 Plan data New consultation addressed only critical‑habitat redesignation and did not remedy earlier alleged failures Court: Claims not moot; post‑2012 consultation did not cure the alleged prior consultation defects
Reinitiation of consultation under 50 C.F.R. § 402.16 2011 Recovery Plan contained new information (short‑term effects, barred‑owl data) triggering reinitiation Forest Service considered short‑term effects and barred‑owl issues; § 402.16 doesn’t require reinitiation for every project change Court: No reinitiation required; record shows Forest Service considered the relevant information and did not act arbitrarily
Use of best scientific and commercial data & NEPA "hard look" Agencies failed to use best available science (2011 Plan, Forsman/Dugger studies) and EISs did not take a hard look at short‑term effects/barred owls Agencies considered the available science, reasonably relied on it, and EISs adequately analyzed short‑term impacts and barred‑owl presence Court: Agencies satisfied ESA and NEPA standards; analyses were reasonable and not arbitrary or capricious

Key Cases Cited

  • Conservation Cong. v. U.S. Forest Serv., 720 F.3d 1048 (9th Cir.) (discussing ESA consultation standards)
  • Forest Guardians v. Johanns, 450 F.3d 455 (9th Cir. 2006) (reinitiation requirement applies to formal and informal consultation)
  • San Luis & Delta-Mendota Water Auth. v. Jewell, 747 F.3d 581 (9th Cir. 2014) (consultation initiation standards)
  • Baltimore Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 462 U.S. 87 (U.S. 1983) (NEPA’s twin aims and procedural purpose)
  • W. Watersheds Project v. Kraayenbrink, 632 F.3d 472 (9th Cir. 2011) (APA standard for reviewing agency action and EIS requirements)
  • Neighbors of Cuddy Mountain v. U.S. Forest Serv., 137 F.3d 1372 (9th Cir. 1998) (NEPA "hard look"/rule‑of‑reason analysis)
Read the full case

Case Details

Case Name: Conservation Congress v. Nancy Finley
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Dec 16, 2014
Citation: 774 F.3d 611
Docket Number: 12-16916
Court Abbreviation: 9th Cir.