History
  • No items yet
midpage
Commonwealth v. Davis
AC 15-P-1088
| Mass. App. Ct. | Jun 2, 2017
Read the full case

Background

  • Defendant Nasahn Davis was arraigned March 19, 2012 on a charge of carrying a firearm without a license; he filed a Mass. R. Crim. P. 36(b) motion to dismiss on March 31, 2014 (742 days later).
  • Rule 36(b) presumes dismissal if trial is not held within 12 months of the return day unless the Commonwealth justifies delay or excluded periods apply.
  • Parties agreed 218 days were properly excluded; dispute centered on whether 268 days of court-congestion-related continuances should also be excluded.
  • Davis objected at each congestion-related continuance and repeatedly sought the next available trial date; the Commonwealth was generally ready for trial and pushed to proceed.
  • Trial court allowed the motion to dismiss; the Appeals Court affirmed, holding court-congestion delays are includable unless (1) the defendant acquiesced/caused/benefited from the delay or (2) the judge made the specific Rule 36(b)(2)(F) findings on the record.

Issues

Issue Commonwealth's Argument Davis's Argument Held
Whether days lost to court congestion and juror unavailability must be excluded from the Rule 36 computation Congestion days should be excluded when the Commonwealth was ready and not at fault; judges implicitly made sufficient findings Congestion days are includable when defendant objected and did not acquiesce, cause, or benefit from the delay Court-congestion delays are included unless defendant acquiesced/caused/benefited or judge made explicit Rule 36(b)(2)(F) findings; here they were included
Whether judges may implicitly satisfy Rule 36(b)(2)(F) by explaining juror unavailability Implicit findings and on-record reasons suffice to exclude delay Rule 36(b)(2)(F) requires express findings on the record that ends of justice outweigh speedy-trial interest Explicit findings are required; mere explanation of juror shortage is insufficient to invoke (F)
Whether defendant’s prior waiver of the 30‑day rule meant acquiescence to initial scheduling delays Waiver of the thirty‑day rule implies acquiescence to the full pre-set trial date Waiver only covers the portion beyond thirty days; initial scheduling does not constitute acquiescence to the whole delay Waiver only covers delay beyond thirty days; the early portion remains includable
Whether defendant benefited from a specific continuance (dismissal of venire) so time should be excluded The jury dismissal gave Davis the benefit of a new venire, so that continuance favored him Davis objected to the continuance; benefit cannot override expressed objection Benefit does not excuse delay when the defendant expressly objected; the period remains includable

Key Cases Cited

  • Commonwealth v. Spaulding, 411 Mass. 503 (1992) (court congestion normally insufficient to justify speedy-trial delay unless defendant agreed)
  • Barry v. Commonwealth, 390 Mass. 285 (1983) (docket and clerk minutes are prima facie evidence; rule 36 balancing of obligations)
  • Commonwealth v. Denehy, 466 Mass. 723 (2014) (defendant who did not object to court-imposed continuances is deemed to have acquiesced)
  • Commonwealth v. Lauria, 411 Mass. 63 (1991) (defendant’s disinterest/acquiescence can permit denial of Rule 36 relief)
  • Commonwealth v. Conefrey, 410 Mass. 1 (1991) (court congestion may be excused when defendant agreed to continuance)
  • Commonwealth v. Rodgers, 448 Mass. 538 (2007) (a claimed benefit to a defendant will not justify delay when the defendant expressly objected to the delay)
Read the full case

Case Details

Case Name: Commonwealth v. Davis
Court Name: Massachusetts Appeals Court
Date Published: Jun 2, 2017
Docket Number: AC 15-P-1088
Court Abbreviation: Mass. App. Ct.