History
  • No items yet
midpage
815 S.E.2d 21
S.C. Ct. App.
2018
Read the full case

Background

  • Laurens Commission of Public Works (LCPW) and City of Fountain Inn both provide municipal natural gas service and met in 1992 to propose a boundary (the "Map") dividing service areas; the Map was never formally ratified.
  • For roughly two decades both municipalities generally observed that boundary while occasionally serving across it with mutual permission.
  • In 2011 LCPW sought to serve ZF Transmissions in Owings Industrial Park, located inside LCPW's portion of the Map; Fountain Inn also bid. LCPW ultimately contracted with ZF.
  • LCPW sued for declaratory relief under S.C. Code § 5-7-60, seeking a declaration that Fountain Inn cannot provide gas service within LCPW’s designated service area without LCPW’s consent; it also sought injunctive relief (temporary injunction denied).
  • At bench trial the court found LCPW had provided service in the contested area for over two decades and had the infrastructure and budgetary certifications to constitute a "designated service area" under § 5-7-60; Fountain Inn appealed.

Issues

Issue Plaintiff's Argument (LCPW) Defendant's Argument (Fountain Inn) Held
Whether LCPW has a § 5-7-60 "designated service area" preventing Fountain Inn from serving customers there without permission LCPW argued long‑term provision of service and budgeted/certified plans establish a designated service area Fountain Inn argued municipalities are limited outside corporate limits and LCPW did not establish a designated service area (or that the Map was not binding) Court held LCPW established a designated service area because it had been providing service and had infrastructure and budgetary certification; Fountain Inn cannot serve there without permission
Proper standard of review Legal standard: statutory interpretation (de novo) Argued equitable standard for injunction/defer to trial judge credibility findings Court applied statutory‑interpretation standard (action at law) because resolution turns on § 5-7-60 construction
Whether the Map itself created a binding boundary/contract LCPW relied on long practice rather than sole reliance on the Map Fountain Inn contended the Map was not a binding contract and could not bind future councils/customers Court resolved case on long‑term practice and provision of service, not on enforceability of the Map, so it did not decide Map as binding contract

Key Cases Cited

  • City of Newberry v. Pub. Serv. Comm'n of S.C., 287 S.C. 404 (S.C. 1986) (discusses § 5-7-60 authority and limits on municipal functions outside corporate limits)
  • Mathis v. Hair, 358 S.C. 48 (Ct. App. 2003) (explains § 5-7-60 defines designated service area as area where service is being provided)
  • Spartanburg Sanitary Sewer Dist. v. City of Spartanburg, 283 S.C. 67 (S.C. 1984) (designated service area found where sewer infrastructure was constructed and serving users)
  • Grier v. AMISUB of S.C., Inc., 397 S.C. 532 (S.C. 2011) (statutory plain‑language rule; courts must follow unambiguous statutory text)
  • Duke Energy Corp. v. S.C. Dep't of Revenue, 415 S.C. 351 (S.C. 2016) (confirms questions of statutory interpretation are questions of law reviewed de novo)
  • Williams v. Town of Hilton Head Island, 311 S.C. 417 (S.C. 1993) (discusses home rule authority of municipalities under Article VIII)
Read the full case

Case Details

Case Name: Comm'rs of Pub. Works of Laurens v. City of Fountain Inn
Court Name: Court of Appeals of South Carolina
Date Published: May 16, 2018
Citations: 815 S.E.2d 21; 423 S.C. 461; Appellate Case No. 2015-001894; Opinion No. 5559
Docket Number: Appellate Case No. 2015-001894; Opinion No. 5559
Court Abbreviation: S.C. Ct. App.
Log In