History
  • No items yet
midpage
Cohen, M. v. JS Associated Service
390 WDA 2017
| Pa. Super. Ct. | Dec 15, 2017
Read the full case

Background

  • In 2007 Cohen discovered a water leak and Travelers recommended ServiceMaster to remediate mold and install a new bathroom subfloor; the parties operated under a written estimate/agreement (Ex. 2a).
  • The Agreement provided ServiceMaster would install a new subfloor in the bathroom but noted permanent finish work would be done by another contractor after remediation.
  • ServiceMaster installed subflooring using glue and screws; Cohen returned to find uneven/poorly fitted subflooring and claimed it was permanently installed and unworkmanlike.
  • Cohen obtained repair estimates: a 2007 estimate from Scott Steel totaling $6,038 (with line items 7–10 totaling $154 to address the subfloor ServiceMaster installed), a later Steel estimate of $11,556 (included leveling and other work beyond the Agreement), and an unsupported $20,000–$25,000 estimate from another contractor.
  • Cohen sued for breach of contract (seeking repair costs and loss of use). After a bench trial the court found breach in Cohen’s favor but awarded $154 (the cost of Steel’s line items 7–10) and denied consequential damages; Cohen appealed.

Issues

Issue Cohen's Argument ServiceMaster's Argument Held
Contract interpretation: whether subfloor was required to be temporary The Agreement required remediation and temporary subflooring to allow finishing; ServiceMaster permanently installed subflooring with glue/screws in breach Agreement only required installation of a new subfloor; it did not specify temporary vs permanent or fastening method, and final flooring was reserved to another contractor Court: contract unambiguous as written; no term required temporary installation — no error in trial court’s contract construction
Measure of damages: proper amount to remedy defective work Trial court should award at least $11,556 (Steel’s in-court estimate) or rely on Eddington’s $20k–$25k lump sum Damages should be limited to cost to complete only work within ServiceMaster’s contractual scope; Steel’s 2007 line items 7–10 ($154) were the relevant, verifiable cost Court: affirmed $154 award; trial court reasonably credited Steel’s testimony that only lines 7–10 were required to complete subfloor work
Credibility/consideration of expert testimony Trial court abused discretion by not considering Steel’s full testimony and by rejecting Eddington’s estimate Trial court properly evaluated witnesses and rejected portions relating to work outside the Agreement Court: appellate deference to factfinder; no abuse of discretion in how the trial court weighed expert testimony
Consequential damages (loss of use) Cohen entitled to damages for loss of use (claimed $300/month) as natural proximate result of breach Any loss was not foreseeable; Cohen failed to mitigate and presented no basis to quantify loss Court: no award for loss of use — not shown foreseeable or supported by evidence; trial court’s discretion affirmed

Key Cases Cited

  • Nicholas v. Hofmann, 158 A.3d 675 (Pa. Super. 2017) (writing controls contract interpretation; parol evidence if ambiguity exists)
  • Epstein v. Saul Ewing, LLP, 7 A.3d 303 (Pa. Super. 2010) (standard of review for adequacy of damages; deference to factfinder)
  • Douglass v. Licciardi Const. Co., Inc., 562 A.2d 913 (Pa. Super. 1989) (measure of damages for defective construction is cost of completion unless disproportionate to diminution in value)
  • Gadbois v. Leb-Co Builders, Inc., 458 A.2d 555 (Pa. Super. 1983) (default rule: damages measured by cost of repairs unless market-value rule applies)
  • Cresci Const. Serv., Inc. v. Martin, 64 A.3d 254 (Pa. Super. 2013) (consequential damages for construction breaches must be foreseeable; award lies within trial court discretion)
Read the full case

Case Details

Case Name: Cohen, M. v. JS Associated Service
Court Name: Superior Court of Pennsylvania
Date Published: Dec 15, 2017
Docket Number: 390 WDA 2017
Court Abbreviation: Pa. Super. Ct.