132 Fed. Cl. 223
Fed. Cl.2017Background
- Clear Creek Community Services District (the District) contracted with the Bureau of Reclamation (BOR) in 1963 for construction, transfer, and delivery of Central Valley Project (CVP) water and operation/maintenance (O&M) arrangements; Part A water provisions expired in 1994 but many contractual duties continued via interim and 2005 long-term contracts.
- BOR completed the Muletown Conduit in 1967 and transferred O&M responsibility to the District; BOR provided design/specification documents and a Designers’ Operating Criteria (DOC).
- Over decades the District experienced valve corrosion, flooded valve vaults, absent or undersized drains and sectionalizing valves, joint sealant failures, variable burial depth, and other defects; engineering reports (PACE) and BOR facility reviews documented these problems from the 1970s through the 2000s.
- The parties executed a 2001 title-transfer of distribution system components and a 2005 long-term water service contract establishing water entitlements and incorporating a then-existing M&I water shortage policy.
- The District sued in 2010 asserting: (1) breach of contract (structural defects and water delivery), (2) inverse condemnation (Fifth Amendment taking of contractual water rights), and (3) declaratory relief. BOR moved to dismiss and for summary judgment; the court considered accrual/limitations under 28 U.S.C. § 2501 and merits of contract and takings claims.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Timeliness of design/construction claims (valve corrosion, flooded vaults, sectionalizing valves, burial depth, joint sealant, records loss) | District contends many defects are latent and their relation to original design/construction was not known until expert work nearer to suit | BOR: District had documents, inspections, facility reviews, and engineering reports dating decades earlier that put District on inquiry notice; claims accrued more than six years before suit | Court: Most structural/design claims accrued no later than 2002 (district was on inquiry notice); those claims are time-barred under §2501 and dismissed for lack of jurisdiction |
| Absence of horizontal drain pipes (as-built vs specs) | District says it only recently discovered that specs called for horizontal drains and that as-built vertical drains differed — factual dispute about whether District knew earlier | BOR argues District had access to design and post-construction records and inspections, so should have known | Court: Genuine issue of material fact exists whether District knew drains were vertical contrary to specs; summary judgment denied on this issue |
| Water delivery / allocation during shortage years (2008–09, 2014–16) | District alleges BOR unlawfully reduced allocations, offset by groundwater pumping, misapplied water shortage policy, and violated area-of-origin rights; seeks damages for emergency water purchases | BOR contends allocations followed the parties’ contract (Article 12) and the then-existing M&I Water Shortage Policy; allocation disputes are governed by contract and administrative process | Court: Multiple genuine factual issues on how allocations were determined and applied; summary judgment denied on water-delivery breach claim |
| Fifth Amendment takings (inverse condemnation) | District contends BOR’s allocation and withholding practices physically deprived it of contractual water rights (15,300 AF) — a compensable taking | BOR argues District’s rights to Project Water arise only from contract; remedies are contractual, not constitutional; area-of-origin statutes don’t create a federal property interest in CVP Project Water | Court: Takings claim fails as a matter of law because the alleged water right exists by contract; summary judgment for BOR granted on takings claim |
| Declaratory/injunctive relief for O&M and water entitlements | District requests declaration that BOR must operate/maintain conduit and not deprive water entitlements contrary to contract and state law | BOR argues Court of Federal Claims has limited equitable jurisdiction and may not grant non-monetary relief beyond its statutory scope | Court: Lacks jurisdiction to grant the requested non-monetary equitable relief; declaratory claim dismissed |
| Loss/destruction of construction records claim | District says BOR failed to preserve construction records, prejudicing District and requiring expert expense | BOR argues no contractual duty to retain those records and District knew records were missing when it assumed O&M in 1967 | Court: Claim untimely — District knew or should have known of missing records in 1967; dismissed for lack of jurisdiction |
Key Cases Cited
- Celotex Corp. v. Catrett, 477 U.S. 317 (summary judgment standard) (establishes movant’s initial burden on summary judgment)
- Anderson v. Liberty Lobby, 477 U.S. 242 (summary judgment standard) (defines materiality and genuine dispute tests)
- John R. Sand & Gravel Co. v. United States, 552 U.S. 130 (statute of limitations in COFC is jurisdictional) (§2501 limitations are jurisdictional and not tolled by equitable tolling)
- Martinez v. United States, 333 F.3d 1295 (Fed. Cir. en banc) (accrual suspension doctrine—knew or should have known standard for §2501)
- Japanese War Notes Claimants Ass’n v. United States, 373 F.2d 356 (Ct. Cl.) (concealed/inherently unknowable injury example; accrual principles)
- Stockton E. Water Dist. v. United States, 583 F.3d 1344 (Fed. Cir.) (permitting alternative pleadings of breach and takings; courts prefer contract remedy when rights arise solely from contract)
- Sun Oil Co. v. United States, 572 F.2d 786 (Ct. Cl.) (interference with contract-created rights generally gives rise to contract, not takings, claims)
