History
  • No items yet
midpage
2014 IL App (1st) 130730
Ill. App. Ct.
2014
Read the full case

Background

  • Cityline (contractor) and Roberts/Gherold (Owners) made an oral agreement (April 2009) for post-fire restoration; Cityline finished work by December 15, 2010.
  • Cityline recorded a mechanic’s lien (Feb 24, 2011) claiming $397,302 and sued to foreclose; Owners counterclaimed seeking a declaration the lien was void.
  • During discovery Owners requested a sworn contractor’s statement (listing subcontractors and amounts); Cityline admitted it never provided one.
  • Cityline produced an affidavit from its VP asserting all subcontractors were paid but did not list names or amounts as required by the Mechanics’ Lien Act §5.
  • Trial court granted partial summary judgment for the Owners voiding the lien; Cityline appealed. Counts for breach of contract and quantum meruit remain pending.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether failure to provide a sworn contractor’s statement (770 ILCS 60/5) when requested voids a mechanic’s lien Cityline: strict compliance should be excused where no prejudice and subcontractors paid; affidavit suffices Owners: statute requires strict, literal compliance; failure to provide sworn names/amounts voids lien The court held the lien is void; strict compliance with §5 is required and cannot be excused by equitable considerations
Whether affidavit that subcontractors were paid satisfies §5 Cityline: VP affidavit shows purpose served; no prejudice Owners: affidavit lacks required names/amounts and is not the sworn contractor’s statement §5 requires Held: affidavit insufficient; it did not list subcontractors or amounts and thus failed §5
Whether First District precedent allows excusing §5 noncompliance Cityline relied on National Wrecking to argue noncompliance can be excused Owners: National Wrecking inapplicable; its holding concerned contract recovery, not lien validity Held: National Wrecking dicta not controlling; §5 governs lien validity and must be strictly followed
Whether equitable considerations (e.g., subcontractors paid) can cure §5 defects Cityline: equity should prevent loss on technicality Owners: creation of mechanic’s lien is statutory; equity cannot alter statutory prerequisites Held: Equity cannot override the Act; strict statutory compliance required

Key Cases Cited

  • Deerfield Electric Co. v. Herbert W. Jaeger & Associates, Inc., 74 Ill. App. 3d 380 (appellate court) (contractor’s failure to provide sworn statement when requested invalidated mechanic’s lien)
  • Weydert Homes, Inc. v. Kammes, 395 Ill. App. 3d 512 (appellate court) (failure to comply with §5 oath/verification requirement invalidates lien; court refused to read exceptions based on timing or notice)
  • Westcon/Dillingham Microtunneling v. Walsh Constr. Co. of Ill., 319 Ill. App. 3d 870 (appellate court) (rights under Mechanics’ Lien Act are statutory and must be strictly construed)
  • National Wrecking Co. v. Midwest Terminal Corp., 234 Ill. App. 3d 750 (appellate court) (discussed distinction between breach of contract recovery and mechanic’s lien validity; dicta that failure to provide sworn statement does not bar lien is not controlling)
Read the full case

Case Details

Case Name: Cityline Construction Fire and Water Restoration, Inc. v. Roberts
Court Name: Appellate Court of Illinois
Date Published: Apr 30, 2014
Citations: 2014 IL App (1st) 130730; 1-13-0730
Docket Number: 1-13-0730
Court Abbreviation: Ill. App. Ct.
Log In
    Cityline Construction Fire and Water Restoration, Inc. v. Roberts, 2014 IL App (1st) 130730