midpage
Projects
Sign in to see your projects.
63 F.4th 835
9th Cir.
2023
Read the full case

Background

  • Bob Hope (Hollywood Burbank) Airport is owned/operated by the Burbank-Glendale-Pasadena Airport Authority; the 14-gate passenger terminal is decades old and does not meet current FAA design/safety standards.
  • A replacement terminal project (northeast-quadrant site; 14 gates; up to 355,000 sq ft) was negotiated with the City of Burbank, subject to CEQA review, and approved by Burbank voters under Measure B in 2016.
  • The Authority submitted an Airport Layout Plan to FAA; FAA prepared a Draft EIS (2019–2020) and issued a combined Final EIS and Record of Decision (ROD) in May 2021 approving the ALP.
  • City of Los Angeles petitioned for review under 49 U.S.C. § 46110, arguing FAA violated NEPA (inadequate alternatives analysis, predetermination, and deficient impacts analyses).
  • FAA used a two-step screening to winnow alternatives (technical/design feasibility & economic/implementation constraints), ultimately analyzing the proposed project and the no-action alternative.
  • The Ninth Circuit: upheld FAA’s purpose-and-need and alternatives analysis, rejected predetermination claim, but found FAA’s construction-noise analysis deficient for failing to aggregate simultaneous equipment noise and remanded to redo construction-noise, cumulative-noise, and related analyses (including reconsideration of environmental justice consistency if warranted).

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Adequacy of purpose & need / range of alternatives LA: FAA’s purpose-and-need and screening improperly narrowed alternatives (excluded reasonable options) and unduly relied on Measure B. FAA: Purpose/need tied to statutory mandates (AAIA) and Authority goals; screening used rational technical/economic criteria; eliminated remote/speculative options. Held: FAA’s purpose-and-need was reasonable and its two-step screening rational; FAA permissibly limited detailed study to feasible alternatives.
Predetermination (Measure B) LA: Including Measure B in screening predetermined outcome and foreclosed meaningful consideration of alternatives. FAA: Measure B was one factor; technical, legal, and economic constraints independently justified rejection of alternatives; no irreversible commitment. Held: No predetermination—FAA did not make an irreversible commitment and could have chosen no-action; inclusion of Measure B did not render the EIS a subterfuge.
Construction-noise analysis LA: FAA failed to take a hard look—assumed single-equipment operation and did not aggregate simultaneous equipment noise, so underestimated impacts. FAA: Calculations and assumptions (distance, intermittent work, existing freeway background) support conclusion that construction noise attenuates below significance thresholds. Held: FAA’s construction-noise analysis was arbitrary/capricious for relying on an unsupported assumption that equipment would not operate simultaneously; remand required to aggregate equipment noise and reassess impacts.
Cumulative impacts & environmental justice LA: Because construction-noise analysis is flawed, FAA’s cumulative-noise and EJ analyses are also defective. FAA: No extensive cumulative analysis needed if project noise is insignificant. Held: Because construction-noise analysis was deficient, FAA must revisit cumulative impacts and related environmental-justice consistency on remand.

Key Cases Cited

  • Robertson v. Methow Valley Citizens Council, 490 U.S. 332 (NEPA prescribes procedures requiring agencies to take a "hard look")
  • Kleppe v. Sierra Club, 427 U.S. 390 (NEPA requires consideration of environmental consequences)
  • Audubon Soc’y of Portland v. Haaland, 40 F.4th 967 (9th Cir. 2022) (rule-of-reason standard for EIS alternatives and impact discussion)
  • WildEarth Guardians v. EPA, 759 F.3d 1064 (9th Cir. 2014) (agency action arbitrary if it fails to consider an important aspect of the problem)
  • Metcalf v. Daley, 214 F.3d 1135 (9th Cir. 2000) (predetermination requires an irreversible commitment of resources)
  • Dep’t of Transp. v. Public Citizen, 541 U.S. 752 (agencies bear primary responsibility to ensure NEPA compliance; some defects may be obvious without commenter's prompting)
  • Env’t Def. Ctr. v. Bureau of Ocean Energy Mgmt., 36 F.4th 850 (9th Cir. 2022) (agency discretion in framing purpose and need but not to unreasonably narrow alternatives)
  • Alaska Survival v. Surface Transp. Bd., 705 F.3d 1073 (9th Cir. 2013) (limits on narrowing alternatives tied to agency purpose and private project context)
Read the full case

Case Details

Case Name: City of Los Angeles v. Faa
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Mar 29, 2023
Citations: 63 F.4th 835; 21-71170
Docket Number: 21-71170
Court Abbreviation: 9th Cir.
Log In