History
  • No items yet
midpage
City of Elgin v. Illinois Commerce Comm'n
2016 IL App (2d) 150047
Ill. App. Ct.
2016
Read the full case

Background

  • ComEd sought an expedited certificate under 220 ILCS 5/8-406.1 to build a 345 kV transmission line (Grand Prairie Gateway) from Byron to Wayne; petition included a primary route (~60 miles) and an alternate for ~80% but provided no alternate for the ~12-mile segment through the City of Elgin.
  • Elgin intervened, opposed the Elgin routing (proximity to residences and an elementary school; aesthetic, land-use, and health concerns), and requested the Elgin segment be placed underground; Elgin did not propose alternate surface routes or produce cost estimates.
  • PJM and ComEd witnesses testified the Byron–Wayne solution best addressed regional congestion; ComEd’s consultant (ERM) described an extensive routing study and public outreach; ComEd claimed no viable alternate through Elgin without excessive length, cost, or residential displacement.
  • Staff performed field inspection, conducted a cost–benefit analysis estimating net benefits of $121.1M–$324.6M, and recommended approval; ALJs initially recommended denial, finding insufficient showing of least-cost and good cause for no Elgin alternate.
  • The Illinois Commerce Commission reversed the ALJs, found ComEd showed good cause to omit an alternate through Elgin, concluded undergrounding was not a viable alternate (cost ~ $31M/mile; ~$396M for 12 miles), and held the Project was the least-cost means overall and equitable to customers; Elgin appealed.

Issues

Issue Plaintiff's Argument (Elgin) Defendant's Argument (ComEd/ICC/Staff) Held
Whether ComEd showed "good cause" for not providing an alternate right-of-way through Elgin ComEd’s showing was conclusory and did not identify rejected alternate surface routes or supporting data in the filing ERM/ComEd presented routing study, public process, and testimony that no viable alternate avoided displacement or excessive length/cost; Staff agreed Commission’s good-cause finding upheld; record evidence (testimony, inspections) is substantial and not against manifest weight
Whether proposing undergrounding in the same strip satisfies the statutory alternate right-of-way requirement Elgin: undergrounding should have been proposed as an alternate and full routing criteria must be considered ComEd/Staff: alternate must be a different route; undergrounding of same ROW does not meet statutory alternate-route requirement; even if considered, undergrounding is cost-prohibitive Court affirmed Commission: undergrounding would more than double project cost (~$396M) and is not a viable least-cost alternative
Whether ComEd proved the Project is the "least-cost" means to satisfy statutory objectives and is equitable to customers Elgin: Commission lacked comparisons and did not meaningfully apply the 12 routing criteria to show least-cost ComEd/Staff: PJM evaluated multiple alternatives; Staff cost–benefit shows net consumer benefits; routing considered multiple factors and existing ROW reduced cost Commission’s least-cost and equity determinations upheld; supported by PJM analysis, Staff cost–benefit, and routing evidence
Whether the Staff failed to adequately investigate good cause and least-cost (CURED argument) Elgin: Staff did not sufficiently investigate, so Commission’s finding is unsupported (invoking CURED) ComEd/Staff: Staff performed discovery, field inspection, cost–benefit analysis, and provided testimony supporting findings; ComEd bears project costs and has incentive to minimize cost CURED distinguished; record shows Staff investigation and independent analysis; Commission’s reliance on Staff was reasonable

Key Cases Cited

  • Illinois Bell Telephone Co. v. Illinois Commerce Comm’n, 327 Ill. App. 3d 768 (2002) (Commission as factfinder entitled to deference on credibility and weight of evidence)
  • Central Illinois Public Service Co. v. Illinois Commerce Comm’n, 268 Ill. App. 3d 471 (1994) (standards for appellate review of Commission orders)
  • Illinois Power Co. v. Illinois Commerce Comm’n, 111 Ill. 2d 505 (1986) (Commission has broad discretion under public-convenience standard)
  • City of Chicago v. Illinois Commerce Comm’n, 264 Ill. App. 3d 403 (1993) (ratepayers should not be required to fund costly undergrounding absent justification)
  • Citizens United for Responsible Energy Development v. Illinois Commerce Comm’n, 285 Ill. App. 3d 82 (1996) (insufficient Staff investigation/cost analysis can require reversal)
Read the full case

Case Details

Case Name: City of Elgin v. Illinois Commerce Comm'n
Court Name: Appellate Court of Illinois
Date Published: Apr 7, 2016
Citation: 2016 IL App (2d) 150047
Docket Number: 2-15-0047
Court Abbreviation: Ill. App. Ct.