History
  • No items yet
midpage
City of Cape Girardeau ex rel. Kluesner Concreters v. Jokerst, Inc.
402 S.W.3d 115
Mo. Ct. App.
2013
Read the full case

Background

  • Jokerst, Inc. was general contractor and Kluesner Con-creters was a concrete subcontractor on the Cape Splash Aquatic Center project; dispute over contract terms and payment obligations.
  • City of Cape Girardeau invited bids; Jokerst provided Kluesner with scope and estimated measurements; Kluesner bid $104,747.40 labeled as an estimate for unit-price work.
  • May 29, 2009, Jokerst informed Kluesner that the project was a lump-sum contract based on Kluesner’s bid and that they would proceed.
  • Kluesner began work in September 2009; issued invoices in Sept. and Nov. 2009 listing units and totals; Jokerst paid those invoices in full.
  • In April–May 2010 Jokerst changed the curb to a stand-up curb; Kluesner issued two extra-work invoices at $30.00 per lineal square foot; Jokerst paid some amounts but left $24,090.00 unpaid for the stand-up curb.
  • After completion, Jokerst sent a final payment of $1,349.82 and asserted it settled the contract based on the original bid; Kluesner sued for the remaining stand-up-curb costs on contract and quantum meruit theories.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a contract existed for unit prices derived from the bid Jokerst: bid used and City award formed contract for unit prices. Kluesner: no mutual assent to a unit-price contract; use of bid does not create contract absent definite practice or promise. No contract formed from bid/award; trial court erred in treating bid as contract.
Whether quantum meruit theory supports recovery for the stand-up curb Jokerst contends no benefit to Kluesner; no unjust enrichment. Kluesner: stand-up curb was requested, had value, and Jokerst refused payment; quantum meruit applies. Kluesner entitled to quantum meruit recovery for stand-up curb; not barred by lack of an express contract.
Whether the judgment is inconsistent by granting relief under both contract theories Jokerst asserts inconsistency and ambiguity. Kluesner's claim properly grounded in quantum meruit only. Judgment affirmed only to the quantum meruit portion; moot as to contract-based relief.
Whether prejudgment interest was properly awarded Jokerst argues damages were unliquidated due to contract dispute. Kluesner contends damages were liquidated by its invoice; prejudgment interest appropriate. Prejudgment interest proper; amount supported by evidence.

Key Cases Cited

  • Murphy v. Carrón, 536 S.W.2d 30 (Mo. banc 1976) (standard of review for court-tried cases)
  • Mortenson v. Leatherwood Constr., Inc., 137 S.W.3d 529 (Mo.App. S.D. 2004) (appellate review; de novo of legal conclusions)
  • Green Quarries, Inc. v. Raasch, 676 S.W.2d 261 (Mo.App. W.D.1984) (elements of quantum meruit; unjust enrichment avoidance)
  • County Asphalt Paving, Co. v. Mosley Constr., Inc., 239 S.W.3d 704 (Mo.App. E.D.2007) (owner payment and unjust enrichment in construction context)
  • Little Joe’s Asphalt v. C.W. Luebbert Constr. Co., 74 S.W.3d 830 (Mo.App. W.D.2002) (quantum meruit; objective reasonableness of rate)
  • Envtl. Waste Mgmt., Inc. v. Indus. Excavating & Equip., Inc., 981 S.W.2d 607 (Mo.App. W.D.1998) (oral contract must have definite terms)
  • KC Excavating, 141 S.W.3d 401, 141 S.W.3d 401 (Mo.App. W.D.2004) (unit price contract; extra work provisions)
  • Massman Constr. Co. v. Kansas City, 487 S.W.2d 470 (Mo. 1972) (lump sum contract included extra work provision)
  • Hutchens v. Burrell Inc., 342 S.W.3d 399 (Mo.App. W.D.2011) (price is material term in contracts)
Read the full case

Case Details

Case Name: City of Cape Girardeau ex rel. Kluesner Concreters v. Jokerst, Inc.
Court Name: Missouri Court of Appeals
Date Published: Jun 11, 2013
Citation: 402 S.W.3d 115
Docket Number: No. ED 98654
Court Abbreviation: Mo. Ct. App.