History
  • No items yet
midpage
897 F.3d 241
D.C. Cir.
2018
Read the full case

Background

  • FERC granted Algonquin a Section 7 certificate for the AIM Project (pipeline upgrade) after preparing an Environmental Impact Statement (EIS). Petitioners include a town, Riverkeeper, and a coalition; City of Boston Delegation's petition was dismissed for lack of jurisdiction.
  • Petitioners challenged the certificate under NEPA, alleging improper segmentation (failure to analyze AIM together with Algonquin’s Atlantic Bridge and Access Northeast projects) and inadequate cumulative impacts analysis.
  • Petitioners also argued the AIM Project increased safety risks to the nearby Indian Point nuclear plant and that FERC relied on a conflicted third‑party contractor (Natural Resource Group) to prepare the EIS.
  • FERC relied on Entergy’s safety evaluation and an independent NRC analysis concluding the pipeline posed no additional safety hazard to Indian Point. Petitioners presented contrary expert critiques.
  • Petitioners did not raise the contractor conflict claim to FERC on rehearing; the court considered CARE to excuse exhaustion and reached the merits of the conflict claim.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
NEPA segmentation — whether FERC should have combined AIM, Atlantic Bridge, and Access Northeast in one EIS FERC impermissibly segmented review and should have analyzed projects together Projects lacked temporal overlap and had independent utility; separate reviews were permissible Court held no arbitrary/capricious action; separate EIS for AIM was permissible
NEPA cumulative impacts — adequacy of cumulative impacts analysis for the three projects FERC failed to adequately analyze cumulative impacts of the three projects FERC considered Atlantic Bridge sufficiently; Access Northeast was too speculative at the time to meaningfully analyze Court held cumulative impacts analysis adequate given information reasonably foreseeable at the time
Safety re Indian Point — whether substantial evidence supports FERC’s conclusion of no increased risk Petitioners’ experts argued AIM posed safety risks and criticized assumptions (e.g., shutdown time) FERC relied on Entergy and NRC analyses (NRC also modeled catastrophic continuous flow) concluding no significant hazard Court held FERC’s safety finding supported by substantial evidence and reasonable crediting of NRC/Entergy experts
Conflict of interest / exhaustion — whether court has jurisdiction and whether contractor conflict invalidates EIS Petitioners alleged Natural Resource Group had a conflict and FERC failed to disclose; they did not raise it on rehearing FERC argued claim was unexhausted; even if considered, no disqualifying conflict and process integrity not compromised Court excused exhaustion under CARE, reached merits, and rejected conflict claim as non‑disqualifying and not compromising NEPA integrity

Key Cases Cited

  • Minisink v. FERC, 762 F.3d 97 (D.C. Cir. 2014) (deference to FERC and standards for NEPA review and substantial evidence)
  • Myersville Citizens for a Rural Cmty. v. FERC, 783 F.3d 1301 (D.C. Cir. 2015) (rule of reason for NEPA cumulative analysis; refusal to flyspeck agency findings)
  • Del. Riverkeeper Network v. FERC, 753 F.3d 1304 (D.C. Cir. 2014) (segmentation doctrine and when related projects must be combined in NEPA review)
  • Sierra Club v. FERC, 867 F.3d 135 (D.C. Cir. 2017) (EIS must discuss relevant issues and opposing viewpoints to show reasoned decisionmaking)
  • Murray Energy Corp. v. FERC, 629 F.3d 231 (D.C. Cir. 2010) (deference to agency resolution of expert disputes)
  • Communities Against Runway Expansion, Inc. v. FAA (CARE), 355 F.3d 678 (D.C. Cir. 2004) (excusing exhaustion where petitioner lacked reason to raise conflict during agency process)
  • Washington Gas Light Co. v. FERC, 532 F.3d 928 (D.C. Cir. 2008) (public interest inquiry includes safety concerns)
  • Theodore Roosevelt Conservation P'ship v. Salazar, 616 F.3d 497 (D.C. Cir. 2010) (project too preliminary to meaningfully estimate cumulative impacts)
Read the full case

Case Details

Case Name: City of Bos. Delegation v. Fed. Energy Regulatory Comm'n
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jul 27, 2018
Citations: 897 F.3d 241; No. 16-1081; C/w 16-1098; 16-1103
Docket Number: No. 16-1081; C/w 16-1098; 16-1103
Court Abbreviation: D.C. Cir.
Log In
    City of Bos. Delegation v. Fed. Energy Regulatory Comm'n, 897 F.3d 241