818 S.E.2d 33
Va.2018Background
- Virginia-American Water Company (VAWC) sought a general rate increase and approval of a water and wastewater infrastructure surcharge (WWISC) to accelerate replacement of aging mains, especially in the Alexandria District.
- VAWC presented engineering and financial evidence showing slow replacement rates, aging cast-iron mains, projected capital needs, and that traditional base-rate cases create regulatory lag for non–revenue-producing infrastructure replacement.
- Opponents (City of Alexandria, City of Hopewell) and expert consultants argued existing ratemaking mechanisms and accounting (depreciation, base-rate cases) were sufficient and raised consumer-protection concerns (need for earnings tests, caps, true-ups).
- A Hearing Examiner recommended a three-year pilot WWISC limited to the Alexandria District with multiple safeguards (7.5% cap, annual Earnings Test, docketed annual filings, audits, refund mechanism, accounting requirements).
- The State Corporation Commission (SCC) approved the three-year pilot WWISC for Alexandria with modifications, including an earnings-based refund obligation if returns exceeded the approved ROE, and authorized VAWC to file to institute the rider.
- Cities appealed, arguing (1) the SCC lacked statutory authority to approve the WWISC outside a base-rate case and (2) the evidence was insufficient to justify the WWISC.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether SCC had statutory authority to approve WWISC | Cities: No statutory authorization for a standalone WWISC; future infrastructure must be accounted for only in base-rate cases | SCC/VAWC: Broad statutory ratemaking authority allows SCC to approve rate mechanisms, subject to statutory standards and safeguards | Court: SCC possessed statutory authority under broad ratemaking statutes (Code §§ 56-235, 56-235.2, etc.) |
| Whether approval violated statutory limits by ignoring returns or revenue effects | Cities: WWISC ignores potential revenue increases or additional profits from infrastructure and thus is outside statutory framework | SCC/VAWC: SCC considered statutory factors, imposed safeguards (Earnings Test, cap, limited pilot) so aggregate revenues remain subject to review | Court: SCC did not ignore statutory factors; safeguards (Earnings Test, cap, annual review) ensure compliance with just-and-reasonable standard |
| Whether SAVE Act or other explicit statutes preclude SCC action absent legislation | Cities: Because SAVE Act specifically governs natural gas rate clauses, similar express authorization is required for water | SCC/VAWC: Presence of special statutes for other contexts does not limit general regulatory authority unless General Assembly clearly so provides | Court: Express grants elsewhere do not negate SCC’s general discretion; absent a clear statutory limit, SCC may act |
| Whether record evidence was insufficient to support WWISC (arbitrary or contrary to evidence) | Cities: Experts and VAWC admissions showed existing mechanisms suffice; no need demonstrated | SCC/VAWC: Substantial evidence (engineering, capital projections, regulatory lag) supported need; SCC entitled to weigh conflicting expert testimony | Court: Substantial evidence supports SCC’s finding WWISC is just and reasonable; appellate court will not substitute its judgment for SCC’s fact-finding |
Key Cases Cited
- City of Norfolk v. Virginia Elec. & Power Co., 197 Va. 505, 90 S.E.2d 140 (Va. 1955) (upholding an "escalator" rate clause tied to changing fuel costs)
- Old Dominion Power Co. v. State Corp. Comm'n, 228 Va. 528, 323 S.E.2d 123 (Va. 1984) (SCC discretion over automatic adjustment clauses reviewed for rational relationship to legitimate purpose)
- BASF Corp. v. State Corp. Comm'n, 289 Va. 375, 770 S.E.2d 458 (Va. 2015) (deference to SCC’s statutory construction but reviewable de novo for legal error)
- Virginia Elec. & Power Co. v. State Corp. Comm'n, 284 Va. 726, 735 S.E.2d 684 (Va. 2012) (SCC decisions entitled to respect as expert tribunal; limits on appellate substitution of judgment)
- Appalachian Power Co. v. State Corp. Comm'n, 284 Va. 695, 733 S.E.2d 250 (Va. 2012) (upholding SCC findings where supported by evidence)
