History
  • No items yet
midpage
Citizens Action Coalition of Indiana, Inc. v. Southern Indiana Gas & Electric Co.
2015 Ind. App. LEXIS 696
| Ind. Ct. App. | 2015
Read the full case

Background

  • Vectren sought approval of clean coal projects and cost recovery mechanisms to meet EPA requirements (MATS, NOV, CAA information request).
  • Intervenors CAC, Sierra Club, Valley Watch, and OUCC opposed, arguing for replacement of coal units with natural gas; OUCC later reversed opposition.
  • Commission approved Mandated Projects and cost deferral; Appellants appealed arguing missing findings on Chapter 8.7 factors and CPCN requirements.
  • Evidence showed alternatives (retire/replace units) versus upgrading existing coal units; B&V and Burns & McDonnell analyses favored continued operation with upgrades.
  • Court remanded to Commission to make explicit findings under Indiana Code sections 8-1-8.7-3 and related chapters for CCT and federally mandated projects.
  • Key issue on appeal was whether the Commission properly applied Chapters 8.7, 8.4, and 8.8 to grant a CPCN and authorize deferrals.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did the Commission fail to make nine-factor findings under 8-1-8.7-3? Appellants: required 8.7-3(b) findings were omitted. Vectren: 8.7 findings unnecessary if 8.4/8.8 relied upon; mootness argued. Remanded to complete 8.7-3 findings.
Are the Brown/Culley/Warrick projects CCT under 8-1-8.8 and does that require a CPCN under 8.7? Appellants: projects meet CCT and trigger CPCN under 8.7. Vectren: some components fall under 8.8/8.4, not 8.7; 8.7 applies only to sulfur/nitrogen reductions. 8.7 applies to sulfur/nitrogen controls; some CCT components require CPCN; remand for 8.7 findings on specific controls.
Was the Commission’s failure to address the necessity of Culley Unit 2 and project load considerations material? Culley 2 may be unnecessary per load forecasts; findings needed. Commission addressed reliability risks and found projects reasonable and necessary. Not error; findings on Culley 2 unnecessary given evidence of reliability risk.
Was Vectren’s delay in filing its application unreasonable and was that issue properly considered? Delay caused reliability risks; should be examined. Delay not shown to be material; not necessary to findings. Not error; court found delay not material to conclusions; no need for findings.

Key Cases Cited

  • Citizens Action Coal. of Ind., Inc. v. Pub. Serv. Co. of Ind., 612 N.E.2d 199 (Ind.Ct.App.1993) (tiered standard of review for IURC orders; substantial evidence required)
  • N. Ind. Pub. Serv. Co. v. United States Steel Corp., 907 N.E.2d 1012 (Ind.2009) (IURC as fact-finding body with expertise; order presumed valid)
  • Columbus Bd. of Zoning Appeals v. Wetherald, 605 N.E.2d 208 (Ind.Ct.App.1992) (appeal not moot when construction proceeds pending appeal)
  • Annexation Ordinance F-2008-15 v. City of Evansville, 955 N.E.2d 769 (Ind.Ct. App.2011) (stay requirements and remonstrance context for mootness)
  • Shumaker v. Shumaker, 559 N.E.2d 315 (Ind.Ct.App.1990) (exclusion of statutory factors may be harmless error)
  • Helm v. Helm, 873 N.E.2d 83 (Ind.Ct. App.2007) (harmless error when statute requirements satisfied by other actions)
  • Jennings Water, Inc. v. Office of Env. Adjudication, 909 N.E.2d 1020 (Ind.Ct. App.2009) (magic words not required if evidence supports conclusion)
Read the full case

Case Details

Case Name: Citizens Action Coalition of Indiana, Inc. v. Southern Indiana Gas & Electric Co.
Court Name: Indiana Court of Appeals
Date Published: Oct 29, 2015
Citation: 2015 Ind. App. LEXIS 696
Docket Number: No. 93A02-1502-EX-110
Court Abbreviation: Ind. Ct. App.