125 F.4th 229
D.C. Cir.2025Background
- Indiana approved a plan to retire a coal-fired electricity facility, replacing it with wind, solar, and two new natural gas turbines to ensure grid reliability.
- To serve those turbines, CenterPoint (the utility) contracted with Texas Gas Transmission for a new 24-mile natural gas pipeline; Texas Gas sought FERC approval for the pipeline.
- Citizens Action Coalition of Indiana challenged FERC’s approval, claiming the commission failed to adequately consider environmental impacts and alternatives under NEPA and the NGA.
- The Indiana Utility Regulatory Commission had previously rejected a larger gas project for insufficiently considering alternatives, but ultimately approved the modified plan including wind, solar, and two smaller gas turbines.
- FERC conducted an environmental impact statement and approved the pipeline; Citizens Action petitioned for review after its rehearing request was denied by operation of law.
- The D.C. Circuit reviewed the agency’s order under the APA’s arbitrary, capricious, or otherwise not in accordance with law standard.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Must FERC analyze non-gas alternatives before approving the pipeline? | FERC had to consider renewable/non-gas alternatives to the pipeline. | FERC only needs to consider alternatives consistent with the state-approved mix. | FERC need not consider non-gas alternatives outside its jurisdiction; only alternatives meeting project’s purpose. |
| Did FERC have to label project emissions as “significant”? | FERC’s failure to label GHG emissions significance was arbitrary/unlawful. | NEPA/CEQ guidance don’t require a significance label; thorough analysis suffices. | No NEPA or regulation requires a significance label; FERC’s contextual discussion of emissions is sufficient. |
| Could FERC consider emissions reductions from retiring coal units? | FERC could not count emissions reductions from retired coal units in analysis. | Net emissions consideration was reasonable in light of Indiana’s energy decisions. | It was reasonable for FERC to consider net (coal-for-gas) emissions when assessing public convenience/necessity. |
| Did FERC fail to adequately respond to Citizens Action’s arguments? | FERC did not meaningfully respond to rehearing arguments on environmental effects. | FERC’s original order sufficiently explained its reasoning and process. | No separate response necessary; initial order provided adequate reasoning for meaningful judicial review. |
Key Cases Cited
- Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190 (D.C. Cir. 1991) (agency’s definition of project purpose must be reasonable and anchored in statutory authority)
- Minisink Residents for Env’t Preservation & Safety v. FERC, 762 F.3d 97 (D.C. Cir. 2014) (FERC may approve project only if public benefits outweigh adverse impacts)
- Food & Water Watch v. FERC, 104 F.4th 336 (D.C. Cir. 2024) (FERC not required to attach significance labels to environmental effects under NEPA)
- Myersville Citizens for a Rural Cmty., Inc. v. FERC, 783 F.3d 1301 (D.C. Cir. 2015) (FERC’s analysis of economic and environmental impacts under NGA)
- NAACP v. FPC, 425 U.S. 662 (1976) (primary NGA purpose is gas supply development; environmental objectives are subsidiary)
- EarthReports, Inc. v. FERC, 828 F.3d 949 (D.C. Cir. 2016) (FERC may reasonably discuss emissions in percentages; social cost of carbon not required under NEPA)
