797 S.E.2d 803
W. Va.2016Background
- Citibank issued Mr. Perry a MasterCard governed by a Card Agreement that included an arbitration clause allowing either party to move to compel arbitration at any time before trial or final judgment and containing a "no waiver" clause.
- Citibank filed a debt-collection suit in Boone County Circuit Court on September 20, 2010; Perry filed a pro se letter-answer conceding the debt on October 1, 2010.
- Citibank moved for judgment on the pleadings in April 2011; the motion was never decided and the case remained largely inactive for ~3.5 years.
- After Perry obtained counsel, the parties submitted an agreed scheduling order; Perry filed a putative class counterclaim (WVCCPA and related claims) on May 1, 2015 (more than four years after the original suit).
- Citibank moved to compel arbitration and stay the action less than two months after Perry’s counterclaim; the circuit court denied the motion, finding Citibank had waived arbitration by litigating and delaying nearly five years.
- The Supreme Court of Appeals reversed, concluding Citibank did not intentionally relinquish the arbitration right and remanded with instructions to compel arbitration and stay the case.
Issues
| Issue | Citibank's Argument | Perry's Argument | Held |
|---|---|---|---|
| Whether Citibank waived its contractual right to arbitrate | Contract permits either party to seek arbitration anytime before trial or final judgment; the no-waiver clause preserves the right; federal policy favors arbitration | Citibank’s initiation of suit, litigation activity, agreed scheduling order, discovery conduct, and long delay caused waiver and prejudice | No waiver: Citibank did not intentionally relinquish the right; motion to compel arbitration must be granted |
| Whether prejudice is required to find waiver | Courts often require actual prejudice before inferring waiver; Citibank acted promptly after counterclaim | Perry contends he was prejudiced by delay and exchanged discovery responses | Court applied WV law: prejudice not required, but here Perry failed to prove waiver and alleged prejudice was insufficient |
| Whether the circuit court properly applied West Virginia law versus contract choice-of-law | Citibank argued choice-of-law clause required South Dakota/federal law; consistency between laws made issue harmless | Perry relied on WV waiver precedent | Issue not preserved below; WV and SD law were treated as consistent; no reversible error |
| Effect of a contractual "no waiver" clause on waiver analysis | Such clauses do not preclude waiver inquiry; ordinary waiver principles still apply | Perry argued actions overcame the clause | Court held no-waiver clause does not automatically bar finding of waiver but here there was no intent to relinquish right |
Key Cases Cited
- Credit Acceptance Corp. v. Front, 231 W.Va. 518, 745 S.E.2d 556 (W.Va. 2013) (interlocutory denial of motion to compel arbitration reviewable de novo)
- Parsons v. Halliburton Energy Servs., Inc., 237 W.Va. 138, 785 S.E.2d 844 (W.Va. 2016) (waiver requires intentional relinquishment; prejudice not required)
- Johnson Assocs. Corp. v. HL Operating Corp., 680 F.3d 713 (6th Cir. 2012) (a contractual no-waiver clause does not foreclose a waiver finding under ordinary principles)
- American Recovery Corp. v. Computerized Thermal Imaging, Inc., 96 F.3d 88 (4th Cir. 1996) (courts will not lightly infer waiver given strong federal policy favoring arbitration)
- S & R Co. of Kingston v. Latona Trucking, Inc., 159 F.3d 80 (2d Cir. 1998) (permitting courts to find waiver despite no-waiver clauses to avoid tactical delay)
- Ara v. Erie Ins. Co., 182 W.Va. 266, 387 S.E.2d 320 (W.Va. 1989) (waiver requires evidence of intentional relinquishment of a known right)
