History
  • No items yet
midpage
126 Conn. App. 18
Conn. App. Ct.
2011
Read the full case

Background

  • On Oct 20, 2007, Cianci and Originalwerks entered a construction contract valued at $1,776,896 for a new house.
  • Originalwerks began work, including demolition and site prep, and continued until July 15, 2008, when Cianci told them to cease work.
  • Cianci hired a consultant and identified deficiencies; Paltauf, owner of Originalwerks, advised not to continue until deficiencies were discussed.
  • On Sept 23, 2008, after Cianci provided a list of deficiencies, Paltauf inspected the property, removed and replaced plywood to review beams, and removed some tools.
  • On Oct 15, 2008, Originalwerks recorded a mechanic's lien for $151,647 plus attorney’s fees; Cianci amended her discharge application on Nov 6, 2008.
  • The court held evidentiary hearings on Dec 1 and Dec 15, 2008; in Feb 2009 the court found probable cause to sustain the lien and held the lien timely under § 49-34.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the lien amount was properly determined Cianci argues the lien amount is improper and not supported by evidence. Originalwerks contends the lien amount reflects materials and services furnished, not profits or total contract value. Lien amountProperly supported; clear and convincing standard not met to reduce amount.
Whether the lien was timely filed under § 49-34 Cianci asserts filing >90 days after cessation of services renders lien untimely. Originalwerks maintains Sept 23, 2008, inspection/response extended the 90-day period; filing on Oct 15, 2008 was timely. Lien timely; Sept 23, 2008 inspection constituted lienable services extending the period.

Key Cases Cited

  • Dreambuilders Contrustion, Inc. v. Diamond, 121 Conn.App. 554 (2010) (evidentiary review of lien amount under § 49-35b)
  • Weber v. Pascarella Mason Street, LLC, 103 Conn.App. 710 (2007) (expands interpretation of services under § 49-33(a))
  • Nickel Mine Brook Associates v. Joseph E. Sakal, P.C., 217 Conn. 361 (1991) (scope of services and site development coverage)
  • Thompson & Peck, Inc. v. Division Drywall, Inc., 241 Conn. 370 (1997) (services must be lienable and contribute to physical improvement)
  • F.B. Mattson Co. v. Tarte, 247 Conn. 234 (1998) (extension doctrine and lienable services removal/installation)
  • 36 DeForest Avenue, LLC v. Creadore, 99 Conn.App. 690 (2007) (ongoing project renders lien timely; lienable services identified)
  • Rollar Construction & Demolition, Inc. v. Granite Rock Associates, LLC, 94 Conn.App. 125 (2006) (liberal construction of mechanic's lien remedial purpose)
  • Martin Tire & Rubber Co. v. Kelly Tire & Rubber Co., 99 Conn. 396 (1923) (defer to required lienable services tied to building repair/aid)
Read the full case

Case Details

Case Name: Cianci v. ORIGINALWERKS, LLC
Court Name: Connecticut Appellate Court
Date Published: Jan 11, 2011
Citations: 126 Conn. App. 18; 16 A.3d 705; 2011 Conn. App. LEXIS 523; AC 30957
Docket Number: AC 30957
Court Abbreviation: Conn. App. Ct.
Log In
    Cianci v. ORIGINALWERKS, LLC, 126 Conn. App. 18