History
  • No items yet
midpage
837 F.3d 146
2d Cir.
2016
Read the full case

Background

  • Chesapeake issued $1.3 billion of senior notes in Feb 2012 governed by a Base Indenture and a Supplemental Indenture that provided two early‑redemption regimes: an "At‑Par" redemption available through March 15, 2013, and a post‑March 15 make‑whole redemption (Make‑Whole Price).
  • Section 1.7(b) allowed redemption at 100% principal (At‑Par) if notice was given 30–60 days before the redemption date; Section 1.7(c) required the Make‑Whole Price for redemptions after March 15, 2013.
  • Chesapeake mailed a March 15, 2013 notice calling for a May 13, 2013 At‑Par redemption. BNY Mellon (indenture trustee) disputed timeliness and asserted the Make‑Whole Price might apply.
  • The district court initially held the notice timely (allowing At‑Par redemption); Chesapeake redeemed on May 13, 2013 and paid At‑Par. This Court reversed on appeal, holding the notice was untimely and remanded.
  • On remand the district court awarded the Noteholders contract damages equal to the difference between the At‑Par amount paid and the Make‑Whole Price (plus prejudgment interest), and entered judgment for ~$438.7 million; Chesapeake appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Measure of recovery for underpayment on early redemption Chesapeake: restitution (return to pre‑redemption position) is the proper remedy after reliance on a judgment later reversed; not contract damages BNY Mellon: New York contract law controls; the indenture sets the remedy and Make‑Whole applies because redemption occurred after March 15 Court: Affirmed contract‑based measure — damages equal to Make‑Whole minus At‑Par + prejudgment interest
Whether restitution displaces contract remedy Chesapeake: doctrine of restitution after reversal requires rescission‑style relief BNY Mellon: restitution is displaced where an enforceable contract governs the subject matter Court: Restitution subordinate to contract here; indenture governs recovery
Whether awarding Make‑Whole over‑compensates Noteholders Chesapeake: Make‑Whole yields more than the actual loss and is inappropriate for an unauthorized prepayment analogy BNY Mellon: Parties voluntarily redeemed; Make‑Whole is the contract price for post‑deadline redemptions Court: Rejects over‑compensation claim — enforcing the contract price respects investor expectations and contract terms
Procedural authority to award damages after declaratory action Chesapeake: (argues remedy should be restitution) BNY Mellon: District Court may grant further relief under 28 U.S.C. § 2202 to effect its declaratory judgment Court: § 2202 was an appropriate mechanism; Chesapeake does not contest this on appeal

Key Cases Cited

  • Bank of N.Y. Tr. Co. v. Franklin Advisers, Inc., 726 F.3d 269 (2d Cir.) (indentures are contracts governed by contract principles)
  • Quadrant Structured Prods. Co. v. Vertin, 23 N.Y.3d 549 (N.Y.) (treating indentures and structured‑product agreements as contracts enforceable under New York law)
  • MacDraw, Inc. v. CIT Group Equipment Financing, Inc., 157 F.3d 956 (2d Cir.) (where a valid written contract governs, quasi‑contract restitution is ordinarily precluded)
  • Clark‑Fitzpatrick, Inc. v. Long Island R.R. Co., 70 N.Y.2d 382 (N.Y.) (invalidates quasi‑contract recovery when an undisputed written agreement covers the dispute)
  • Northwestern Fuel Co. v. Brock, 139 U.S. 216 (U.S.) (restitution awarded where a court entered a judgment it had no authority to render; distinguished in this case)
Read the full case

Case Details

Case Name: Chesapeake Energy Corp. v. Bank of New York Mellon Trust Co., N.A.
Court Name: Court of Appeals for the Second Circuit
Date Published: Sep 15, 2016
Citations: 837 F.3d 146; 2016 U.S. App. LEXIS 16865; 2016 WL 4895581; 15-2366-cv
Docket Number: 15-2366-cv
Court Abbreviation: 2d Cir.
Log In