History
  • No items yet
midpage
Central Texas Express Metalwork LLC d/b/a Express Contracting
ASBCA No. 61109
| A.S.B.C.A. | Sep 7, 2017
Read the full case

Background

  • In 2011 the Air Force awarded CTEM Contract No. FA3047-11-C-0023 to perform HVAC work for $2,457,237; the contract required a release of claims for final payment.
  • CTEM subcontracted work to IMS; IMS later sued CTEM and the parties settled, with CTEM agreeing to sponsor IMS’s claim against the government.
  • In November 2013 CTEM and the CO agreed to reduce scope (a $286,645.41 credit to the Air Force) and a $62,421.68 equitable adjustment to CTEM; CTEM reserved an intent to file additional delay claims.
  • CTEM submitted a certified REA in September 2014 seeking $643,841.88 (including $345,691.07 for IMS). In May 2016 the parties negotiated a settlement: the Air Force would pay the remaining contract balance of $395,727.99 in exchange for CTEM’s delivery of a final invoice and a broad release.
  • CTEM’s president signed the release on June 2, 2016; DFAS attempted payment, CTEM’s bank returned the EFT and CTEM sought to rescind/modify the payment. CTEM later submitted a certified claim for $643,841.88; the CO denied it as released. CTEM appealed to the ASBCA.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether CTEM's post‑settlement claim is barred by the signed release CTEM argues no final payment occurred because it refused/blocked the EFT, so the release is unenforceable Government argues CTEM executed a release in consideration of final payment under the contract and acceptance created a binding settlement; release bars remaining claims Release enforceable; settlement formed and final payment obligation created a binding contract; claim barred
Whether the release lacked consideration CTEM contends there was no new consideration supporting release Government contends the contract required a release at final payment (contract is consideration) and the Air Force forewent a contractual credit as additional consideration Release was supported by the contract’s final‑payment provision; foregone credit also provided consideration if treated as a modification
Whether the release excepted a sponsored subcontractor claim (IMS) CTEM asserts the CO knew CTEM was sponsoring IMS’s claim, so final payment should not bar that sponsored claim Government contends IMS’s sponsored claim was part of the settled amount and there was no evidence CO understood any additional uncompensated right remained Release covered the sponsored IMS claim because it was part of the settled claim and there was no evidence the CO knew CTEM sought additional compensation beyond the settlement
Whether any equitable exceptions (fraud, duress, mutual mistake) save CTEM’s claim CTEM did not advance specific equitable defenses in opposition Government notes no such defenses were alleged or shown No equitable exception applied; CTEM did not assert or prove fraud/duress/mistake

Key Cases Cited

  • Celotex Corp. v. Catrett, 477 U.S. 317 (summary judgment standard)
  • Anderson v. Liberty Lobby, 477 U.S. 242 (summary judgment and drawing inferences)
  • Mingus Constructors, Inc. v. United States, 812 F.2d 1387 (final release with final payment bars contract claims)
  • Anderson v. United States, 344 F.3d 1343 (contract formation principles — acceptance and revocation)
  • Dairyland Power Coop. v. United States, 16 F.3d 1197 (non‑movant burden at summary judgment where it bears proof at trial)
  • Metcalf Constr. Co. v. United States, 742 F.3d 984 (duty of good faith and fair dealing in contract performance)
Read the full case

Case Details

Case Name: Central Texas Express Metalwork LLC d/b/a Express Contracting
Court Name: Armed Services Board of Contract Appeals
Date Published: Sep 7, 2017
Docket Number: ASBCA No. 61109
Court Abbreviation: A.S.B.C.A.