History
  • No items yet
midpage
Centerplan Construction Co., LLC v. Hartford
343 Conn. 368
| Conn. | 2022
Read the full case

Background

  • City contracted with Pendulum (architect), then with DoNo (developer) and Centerplan (design‑builder); all three also signed a Direct Agreement.
  • City assigned its Architect Agreement to Centerplan/DoNo in May 2015.
  • DoNo sent a claim in Dec. 2015 asserting city-made design changes increased scope; city and DoNo executed a term sheet (Jan. 19, 2016) extending substantial completion to May 17, 2016, forbidding new design changes without the city’s consent, and modifying liquidated damages; Centerplan did not sign the term sheet.
  • Substantial completion missed; city terminated DoNo’s and Centerplan’s contracts in June 2016 and sought liquidated damages.
  • Trial court ruled pretrial that plaintiffs controlled the architect and were liable for architect errors; it excluded most pre‑term‑sheet evidence and instructed the jury to decide only who was to blame for missing the May 17, 2016 deadline. Jury found for the city and awarded $335,000; plaintiffs appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Who had legal control/responsibility for the architect and design across time periods? Plaintiffs: contracts do not unambiguously give them control for all periods; city retained control earlier and term sheet altered control. City: the contracts (Developer, Builder, Assignment) unambiguously gave plaintiffs control and responsibility for architect/design. Court: control splits by period—city had legal control Feb–May 2015; plaintiffs had control May–Jan 2016 (assignment); control Jan–June 2016 (post‑term sheet) is ambiguous and factbound.
Did the term sheet waive plaintiffs’ rights to pursue pre‑term‑sheet claims? Plaintiffs: term sheet did not fully waive preterm claims (esp. DoNo’s) and did not bar evidence of pre‑assignment design errors. City: term sheet resolved/waived all preterm disputes; plaintiffs cannot relitigate those issues. Court: term sheet waived Centerplan’s preterm claims (because city withdrew counterclaims and condition precedent failed), but did not waive DoNo’s claims; trial court improperly precluded DoNo from pursuing preterm claims.
Did the term sheet eliminate Centerplan’s contractual/common‑law right to notice and an opportunity to cure before termination? Plaintiffs: term sheet is silent and cannot be read to waive notice and cure; rights survive or require express waiver; at minimum ambiguity requires jury determination. City: term sheet gave city an absolute right to remove Centerplan for missing the extended deadline (no cure required), preserving the bargain. Court: term sheet is ambiguous on whether city gained a new, unqualified termination right or received an assignment of DoNo’s preexisting right; regardless, Centerplan retained at least an implied/common‑law right to notice and cure (or contractual cure if assignment), so the trial court erred in removing that issue from the jury.
Effect of May 2015 assignment—did it transfer liability for pre‑assignment design errors? Plaintiffs: assignment covered only part C (construction administration) and should not shift liability for earlier design errors to them. City: assignment transferred the Architect Agreement and made plaintiffs responsible for architect and any subsequent errors. Court: assignment plainly transferred full contract rights and control to plaintiffs as of May 2015 (so plaintiffs liable for post‑assignment errors) but the city retained obligations/liability for architect services/errors arising before the assignment.

Key Cases Cited

  • Cruz v. Visual Perceptions, LLC, 311 Conn. 93 (2014) (contracts are ambiguous only if reasonably susceptible to more than one meaning; interpretation is plenary review)
  • United Illuminating Co. v. Wisvest‑Connecticut, LLC, 259 Conn. 665 (2002) (multiple writings on same transaction read together)
  • Tomey Realty Co. v. Bozzuto’s, Inc., 168 Conn. App. 637 (2016) (subsequent agreements and amendments must be given effect when construing rights)
  • Joseph General Contracting, Inc. v. Couto, 317 Conn. 565 (2015) (third parties generally are not bound by contracts absent their assent)
  • Semac Electric Co. v. Skanska USA Building, Inc., 195 Conn. App. 695 (2020) (court reluctant to assume futility when contractually specified cure period exists)
  • Grovenburg v. Rustle Meadow Associates, LLC, 174 Conn. App. 18 (2017) (consenting body can exercise broad design control via consent/withholding authority)
Read the full case

Case Details

Case Name: Centerplan Construction Co., LLC v. Hartford
Court Name: Supreme Court of Connecticut
Date Published: May 24, 2022
Citation: 343 Conn. 368
Docket Number: SC20526
Court Abbreviation: Conn.