History
  • No items yet
midpage
67 F.4th 1176
D.C. Cir.
2023
Read the full case

Background

  • Alaska Gasline Development Corporation proposed the Alaska LNG Project: an ~800-mile, 42-inch pipeline from the North Slope to southern Alaska plus liquefaction/export facilities, intended to commercialize surplus North Slope gas for at least 30 years.
  • FERC prepared a ~1,500-page Environmental Impact Statement (EIS) under NEPA, found a range of environmental impacts, and authorized the project subject to 165 environmental conditions under its delegated NGA authority.
  • Petitioners (Center for Biological Diversity and Sierra Club, “CBD”) challenged the Authorization and FERC rehearing denial in the D.C. Circuit, raising NEPA and NGA public-interest claims.
  • The court reviews NEPA claims under the APA’s arbitrary-and-capricious standard and enforces the NGA’s exhaustion requirement for issues raised before FERC.
  • The court held some issues unexhausted (jurisdictionally barred) and denied the remainder on the merits, upholding FERC’s authorization.

Issues

Issue Plaintiff's Argument (CBD) Defendant's Argument (FERC) Held
Alternatives / No-action analysis FERC improperly conflated true no-action and likely no-action and failed to evaluate alternatives across all impact dimensions FERC reasonably rejected true no-action as not meeting project purpose, considered likely no-action, and need not analyze every alternative to identical depth Upheld FERC; analysis reasonable; claim about alternate pipeline route not exhausted and dismissed
Social Cost of Carbon (SCC) FERC must use SCC or otherwise quantify climate damages under NEPA and 40 C.F.R. §1502.22 SCC methodology is not sufficiently settled or translatable into environmental-impact findings; FERC reasonably declined to use it Upheld FERC on merits (EarthReports precedent); SCC theory under §1502.22 not exhausted before FERC and therefore jurisdictionally barred
Indirect GHG emissions (upstream/downstream/exports) FERC must assess indirect emissions including effects of exports and downstream combustion DOE controls export authorizations; FERC lacks jurisdiction over exports; downstream uses not reasonably foreseeable for Alaska-bound gas Upheld FERC; exports are outside FERC’s NEPA obligations and Alaska-bound downstream emissions were too speculative to require analysis
Cook Inlet beluga impacts (vessel noise and cumulative effects) EIS inadequately analyzed vessel noise impacts and cumulative harms to the endangered beluga population EIS and NMFS Biological Assessment analyzed noise, acknowledged risks, and imposed mitigation; cumulative-impact analysis identified other projects and found minor cumulative effects Upheld FERC; EIS took a ‘‘hard look’’ and imposed reasonable mitigation; cumulative analysis adequate
Wetlands acreage discrepancy FERC’s wetlands impact estimate conflicts with the Corps/Applicant estimate, undermining its analysis Differences explained by distinct scopes and methodologies; FERC consulted Corps and reconciled >99% of the gap Upheld FERC; explanation reasonable and EIS adequate
NGA public-interest determination Authorization fails the NGA public-interest standard because of NEPA deficiencies and unaddressed harms FERC reasonably found substantial economic benefits that outweigh projected environmental impacts and followed NEPA procedures Upheld FERC; public-interest determination reasonable and lawful

Key Cases Cited

  • Balt. Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 462 U.S. 87 (NEPA requires agencies to take a "hard look" at environmental consequences)
  • EarthReports, Inc. v. FERC, 828 F.3d 949 (upholding FERC’s refusal to apply the social cost of carbon under NEPA)
  • Vecinos para el Bienestar de la Comunidad Costera v. FERC, 6 F.4th 1321 (addressing applicability of NEPA methodology regulations to SCC analysis)
  • Delaware Riverkeeper Network v. FERC, 753 F.3d 1304 (connected actions and cumulative-impact analysis principles)
  • Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752 (agencies may not base NEPA decisions on effects outside their statutory authority)
  • Lemon v. Geren, 514 F.3d 1312 (NEPA is procedural and does not compel particular policy outcomes)
  • Minisink Residents for Env’t Preservation & Safety v. FERC, 762 F.3d 97 (courts should not "flyspeck" an EIS)
  • W. Va. Pub. Servs. Comm’n v. Dep’t of Energy, 681 F.2d 847 (NGA manifests a presumption favoring facility authorization)
Read the full case

Case Details

Case Name: Center for Biological Diversity v. FERC
Court Name: Court of Appeals for the D.C. Circuit
Date Published: May 16, 2023
Citations: 67 F.4th 1176; 20-1379
Docket Number: 20-1379
Court Abbreviation: D.C. Cir.
Log In
    Center for Biological Diversity v. FERC, 67 F.4th 1176