789 F.3d 821
8th Cir.2015Background
- Cedar Rapids Lodge & Suites hired North Dakota architect Lightowler Johnson Associates to design an AmericInn hotel; Lightowler’s standard form contract specified North Dakota law.
- Lightowler delivered plans in November 2003, issued revisions through February 2004, and participated in a July 26, 2004 site visit; its last project communication was September 24, 2004.
- AmericInn and Lightowler exchanged reports identifying design/construction deficiencies in late 2003–2004; the hotel opened December 9, 2004, but never received a final certificate of occupancy (denied October 2006).
- Cedar Rapids Lodge sued various parties in federal court on December 3, 2009, asserting, inter alia, professional negligence against Lightowler; the district court granted Lightowler summary judgment as time-barred.
- On appeal, the parties disputed whether North Dakota’s two-year or Iowa’s five-year statute of limitations applied; plaintiff argued tolling (adverse domination/continuous representation) to keep the Iowa claim timely.
- The Eighth Circuit affirmed, holding the negligence claim against Lightowler was untimely under either state’s law and declined to extend tolling doctrines as plaintiff proposed.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Which state’s limitations period governs and whether claim is timely | Iowa law (5‑year) applies and claim filed within 5 years of accrual | North Dakota law (2‑year) applies; claim untimely under either rule | Even assuming Iowa law, claim is untimely; affirmed summary judgment |
| Does adverse domination toll the limitations period for claims against a non‑agent third party | Tolling should apply until adverse governors were removed (Oct 2008) | Adverse domination should not be extended to third‑party negligence claims absent conspiracy/agency | Court declined to extend doctrine to arms‑length third‑party negligence; tolling not available |
| Does the continuous representation (continuous‑service) doctrine delay accrual until substantial completion (Dec 9, 2004) | Accrual should wait until construction substantially completed while architect’s services were ongoing | Plaintiff had notice before completion; accrual under discovery rule occurred earlier | Court refused to adopt continuous representation to delay accrual where plaintiff knew or should have known before completion |
| When did cause of action accrue under Iowa discovery rule | Plaintiff: accrual at or after Dec 9, 2004 (within 5 years) | Defendant: accrual occurred by Nov 2003–2004 based on reports, letters, and site visits | Accrual occurred earlier; objective notice/records show plaintiff should have discovered claims more than five years before suit |
Key Cases Cited
- Walker v. Thielen Motors, Inc., 916 F.2d 450 (8th Cir.) (procedural note on applying state accrual rules in federal court)
- Resolution Trust Corp. v. Armbruster, 52 F.3d 748 (8th Cir. 1995) (discussion of adverse domination doctrine)
- K&W Elec., Inc. v. State, 712 N.W.2d 107 (Iowa 2006) (Iowa discovery rule: accrual when actual or imputed knowledge exists)
- McClendon v. Beck, 569 N.W.2d 382 (Iowa 1997) (continuous‑treatment tolling in medical malpractice)
- Ratcliff v. Graether, 697 N.W.2d 119 (Iowa 2005) (no tolling if plaintiff knew or reasonably should have known before treatment ended)
- Bob McKiness Excavating & Grading, Inc. v. Morton Bldgs., 507 N.W.2d 405 (Iowa 1993) (statute of repose runs from completion for certain improvements to real property)
