History
  • No items yet
midpage
Carson Hybrid Energy Storage v. Turlock Irrigation District CA5
F087073A
Cal. Ct. App.
Feb 5, 2025
Read the full case

Background

  • Carson Hybrid Energy Storage ("Carson") entered an Interconnection System Impact Study Agreement (ISISA) with Turlock Irrigation District ("Turlock") to facilitate connecting their energy storage project to Turlock’s electric transmission system.
  • Carson alleged Turlock breached the ISISA: not following agreed modeling parameters, delaying required studies, refusing to provide invoices, and improperly prioritizing Turlock’s own project over Carson’s.
  • Carson filed both a state court breach of contract suit and an application with the Federal Energy Regulatory Commission (FERC) seeking an order requiring interconnection and transmission services.
  • FERC put its proceedings on hold pending further studies, indicating it required more information before issuing any orders; it clarified Carson could challenge study results later.
  • Turlock demurred in state court on the basis of federal preemption, arguing FERC’s authority preempted Carson’s contract claims; the trial court agreed and dismissed Carson’s suit with prejudice.
  • The California Court of Appeal reversed, holding most of Carson’s claims were not preempted and remanded for further proceedings.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does FERC’s authority under the FPA preempt state breach of contract claims regarding interconnection agreements with non-public utilities? Contract enforcement is a state law matter; FERC's authority is not exclusive. FERC’s exclusive jurisdiction under the FPA preempts any state law claim. Not preempted; FERC and state courts have concurrent jurisdiction.
Did Carson’s requested relief directly conflict with any existing FERC order? No direct conflict exists; FERC hasn't adjudicated contract breach. Carson’s state suit would interfere with the FERC process and orders. No current conflict preemption; hypothetical conflicts insufficient.
Does FERC’s ongoing abeyance and study requirement bar state court claims? FERC is still gathering facts; state breach of contract claims remain open. FERC’s abeyance order implies exclusive jurisdiction until studies are done. Abeyance does not bar contract enforcement claims; no final adjudication.
Are all forms of injunctive relief sought by Carson preempted? Not all injunctive relief overlaps with FERC’s authority, e.g., invoices. Any relief interfering with interconnection/study process is preempted. Certain relief (re: transmission request) is preempted, but much is not.

Key Cases Cited

  • Southern Cal. Edison Co. v. Public Utilities Com., 121 Cal.App.4th 1303 (Cal. Ct. App. 2004) (preemption where state regulation contravenes FERC-issued orders on interconnection agreements)
  • Central Iowa Power Co-op. v. Midwest Independent Transmission System Operator, Inc., 561 F.3d 904 (8th Cir. 2009) (concurrent jurisdiction over interpreting FERC-approved contracts)
  • City of Osceola, Ark. v. Entergy Arkansas, Inc., 791 F.3d 904 (8th Cir. 2015) (courts and FERC share jurisdiction in interpreting energy contracts)
  • Gulf States Utilities Co. v. Alabama Power Co., 824 F.2d 1465 (5th Cir. 1987) (federal preemption may be partial, not total, for contract claims relating to energy regulation)
Read the full case

Case Details

Case Name: Carson Hybrid Energy Storage v. Turlock Irrigation District CA5
Court Name: California Court of Appeal
Date Published: Feb 5, 2025
Citation: F087073A
Docket Number: F087073A
Court Abbreviation: Cal. Ct. App.