History
  • No items yet
midpage
CANO, INC. v. MICHEL JUDET
20-1509
| Fla. Dist. Ct. App. | Sep 22, 2021
Read the full case

Background

  • In 2016 Judet contracted with Cano to repair lightning damage to his home for a fixed price of $300,000, payable in $30,000 draws. Cano began work and Judet paid $90,000.
  • The parties stipulated before trial that Cano had not obtained required electrical and plumbing permits.
  • Judet terminated Cano for breach after discovering the lack of permits; Cano recorded a $40,000 construction lien and sued to foreclose and for breach/unjust enrichment. Judet counterclaimed seeking discharge of the lien and restitution for overpayment.
  • At non-jury trial both sides offered valuation experts; the court found Judet’s expert credible and set the reasonable value (quantum meruit) of Cano’s work at $49,150.
  • The trial court ruled Cano materially breached, invalidated the lien, and entered judgment awarding Judet the difference between payments made ($90,000) and the work’s value ($49,150) — $40,850. Cano appealed.
  • The Fourth District affirmed, holding the trial court applied an appropriate measure of damages and committed no reversible procedural error.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did Cano materially breach the contract by failing to obtain permits and substantially perform? Judet: yes; failure to obtain permits was a material breach permitting termination. Cano: denied material breach. Trial court found Cano committed the first material breach; appeal affirmed.
Was the trial court’s measure of damages improper (wrong legal standard)? Judet: he treated the breach as total and sought rescissory relief — return of payments less quantum meruit value. Cano: court should have applied benefit-of-the-bargain measure (cost to complete or contract price minus cost to finish). Court held rescissory damages were proper because Judet treated breach as total; returning overpayments less quantum meruit value was correct.
Did the court violate Perlow by entering Judet’s proposed final judgment? Judet: trial court properly considered proposals, waited ~30 days, and gave parties time to object. Cano: trial court improperly entered Judet’s proposed judgment in violation of Perlow. Perlow was inapposite; Strand and the record showed no reversible procedural error.
Did the court decide an issue outside the pretrial stipulation by awarding overpayment recovery? Judet: his pleadings and trial arguments sought that relief; awarding restitution was a necessary consequence of finding Cano owed only quantum meruit. Cano: pretrial stipulation did not expressly list recovery by Judet; court exceeded stipulation. Court may decide ancillary relief necessary to effect its rulings; Broche supports allowing judgment for overpayment as implicit in the stipulated issues.

Key Cases Cited

  • Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037 (Fla. 1982) (adopted Restatement measure for benefit-of-the-bargain damages in construction cases).
  • Forbes v. Prime Gen. Contractors, Inc., 255 So. 3d 448 (Fla. 2d DCA 2018) (explains owner’s alternative remedies: rescissory restitution or benefit-of-the-bargain cost-to-complete/market-value approach).
  • Perlow v. Berg-Perlow, 875 So. 2d 383 (Fla. 2004) (procedural limitations on trial court entry of proposed judgments).
  • Strand v. Escambia Cnty., 992 So. 2d 150 (Fla. 2008) (distinguishing Perlow circumstances; procedural context for proposed judgments).
  • Broche v. Cohn, 987 So. 2d 124 (Fla. 4th DCA 2008) (court may award relief not listed in pretrial stipulation if necessary consequence of its primary rulings).
  • Rector v. Larson’s Marince, Inc., 479 So. 2d 783 (Fla. 2d DCA 1985) (discusses available remedies for total breach and precontract restitution).
Read the full case

Case Details

Case Name: CANO, INC. v. MICHEL JUDET
Court Name: District Court of Appeal of Florida
Date Published: Sep 22, 2021
Docket Number: 20-1509
Court Abbreviation: Fla. Dist. Ct. App.